The construction of the bridge shown in this video is part of a $350,000,000 project that upgrades and grade-separates 13 miles of US 31 between I-465 and Indiana State Road 38. The upgraded 13-mile stretch features 11 new interchanges and eliminates 32 traffic signals. Construction on the bridge began in May 2015 and was complete by October 2015, while the overall project was substantially complete by December 2015. This video shows a 4-month time-lapse of the construction of the bridge over 169th Street in 1 minute.
The project is located at 40.0326269,-86.1349337.