Next Article in Journal
Food Literacy and Dietary Intake in German Office Workers: A Longitudinal Intervention Study
Next Article in Special Issue
Application of “Behind the Barriers” Model at Neighbourhood Scale to Improve Water Management under Multi-Risks Scenarios: A Case Study in Lyon, France
Previous Article in Journal
Discrimination against and Associated Stigma Experienced by Transgender Women with Intersectional Identities in Thailand
Previous Article in Special Issue
Meteorological Drought Variability and Its Impact on Wheat Yields across South Africa
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

Hydrological Analysis of Batu Dam, Malaysia in the Urban Area: Flood and Failure Analysis Preparing for Climate Change

by
Siti Mariam Allias Omar
1,*,
Wan Noorul Hafilah Wan Ariffin
1,
Lariyah Mohd Sidek
1,
Hidayah Basri
1,
Mohd Hazri Moh Khambali
2 and
Ali Najah Ahmed
1
1
Sustainable Technology and Environment Group, Institute of Energy Infrastructure, Universiti Tenaga Nasional (UNITEN), Kajang 43000, Malaysia
2
Dam and Design Division, Drainage and Irrigation Department, Kuala Lumpur 50480, Malaysia
*
Author to whom correspondence should be addressed.
Int. J. Environ. Res. Public Health 2022, 19(24), 16530; https://doi.org/10.3390/ijerph192416530
Submission received: 23 September 2022 / Revised: 3 November 2022 / Accepted: 7 November 2022 / Published: 9 December 2022
(This article belongs to the Special Issue Hydrological Responses to Climate Change)

Abstract

:
Extensive hydrological analysis is carried out to estimate floods for the Batu Dam, a hydropower dam located in the urban area upstream of Kuala Lumpur, Malaysia. The study demonstrates the operational state and reliability of the dam structure based on hydrologic assessment of the dam. The surrounding area is affected by heavy rainfall and climate change every year, which increases the probability of flooding and threatens a dense population downstream of the dam. This study evaluates the adequacy of dam spillways by considering the latest Probable Maximum Precipitation (PMP) and Probable Maximum Flood (PMF) values of the concerned dams. In this study, the PMP estimations are applied using comparison of both statistical method by Hershfield and National Hydraulic Research Institute of Malaysia (NAHRIM) Envelope Curve as input for PMF establishments. Since the PMF is derived from the PMP values, the highest design flood standard can be applied to any dam, ensuring inflow into the reservoirs and limiting the risk of dam structural failure. Hydrologic modeling using HEC-HMS provides PMF values for the Batu dam. Based on the results, Batu Dam is found to have 200.6 m3/s spillway discharge capacities. Under PMF conditions, the Batu dam will not face overtopping since the peak outflow of the reservoir level is still below the crest level of the dam.

Graphical Abstract

1. Introduction

A dam can be considered a large dam if its height from the foundation is 15 m or higher, or between 5 and 15 m, and its storage capacity is larger than three million cubic meters as defined by the International Commission on Large Dams (ICOLD) [1]. Large dam failure raises concerns in many nations because of the serious economic and social consequences that might result from it [2]. The hydrological regime may alter the dam’s usual condition as a result of climate change and runoff will likely shift significantly in the 21st century as a result of changing rainfall patterns and rising temperatures [3]. In common usage, the term “hydrology” now refers to research on precipitation and runoff that has been connected to issues with the design and management of water resource projects including dam functioning as flood control and water supply [4].
Traditional dam design methods concentrate on deterministic consideration of severe occurrences, such as the probable maximum flood (PMF). The PMF is the maximum amount of flooding a logically possible set of meteorological and hydrologic circumstances might possibly expect. In other words, PMF assumes the dependability of zero failure while taking into account the maximum range of flood potential [5]. PMF is usually estimated by using Probable Maximum Precipitation, which also known as PMP using as an input in hydrologic modeling software.
The PMP over the study region is needed to calculate the PMF against the dam. There are several methods available for PMP estimation which can be categorized as hydrometeorological and statistical [6,7,8]. The meteorological approach is based on maximization of atmospheric moisture content during intense storm conditions, whereas the statistical approach is based on frequency-based statistical analysis and is computed using maximum rainfall occurred over historical periods and standard deviation of annual maximum rainfall [8]. The moisture maximization method, storm transposition method, generalized method, storm separation method, and depth-area duration method are all common hydrometeorological methods. The Hershfield method and its variants, as well as the multifractal approach, are common statistical methods [7]. It has the advantages of taking real historical data in the area of interest into consideration, describing it in terms of statistical characteristics, and being simple to apply [8,9].
The common potential failure mode for the dam will be overtopping. In order to prevent overtop at the dam crest, a study is conducted for the hydrological evaluation to determine if the dam has the spillway capacity to safely manage the PMF. This typical method for calculating the hydrological risk of dam overtopping is based on a univariate analysis that only takes into account flood peak discharges from the most PMF [5,10,11].
In this paper, the study area will be the Batu Dam, which is located in the urban area of Kuala Lumpur in the country of Malaysia. The primary objective of this study is to perform hydrological analysis including rainfall time series and double mass curve to verify the reliability of the hydrological data. Then, an analysis of PMP is conducted by comparing two statistical methods of Hershfield’s [12,13] and by NAHRIM envelope curve specifically for Peninsular Malaysia [14], which then will be an input to estimate the PMF for dam safety check with the spillway design capacity to predict the probability of overtopping.

2. Materials and Methods

2.1. Study Area

In response to the disastrous flood that hit Kuala Lumpur in 1971, USBR (The United States Bureau of Reclamation) developed the flood control and water supply dam known as Batu Dam as part of the Kuala Lumpur Flood Mitigation (KLFM) Project. It began to be constructed in 1985 and was finished in 1987. Approximately 20 km north of Kuala Lumpur, the Batu Dam catchment is situated in Peninsular Malaysia at 3°16′20′′ N latitude and 101°41′9′′ E longitude. The Batu Dam location is near Gombak Selangor, about 16 km upstream of the Kuala Lumpur city center, and is situated just downstream of the meeting point of two rivers known locally as Sungai Batu and Sungai Tua [15].
The Batu dam is built on schist, with schistosity dipping downstream. This schist is weathered to varied degrees, ranging from entirely weathered to fresh. The foundation of the embankment’s core zone and upstream part is made of weathered and fresh schist, whereas the foundation of the embankment’s downstream section is made of alluvial gravel layer [16]. Batu Dam is located in state of Selangor, which has an equatorial climate that is heavily influenced by the East Asian Monsoon. Selangor typically has two rainy seasons every year, with the south west monsoon from June to September and the north monsoon from November to March [17,18]. The Batu Reservoir was constructed to be used as a water supply for municipal and industrial purposes, as sediment management, and to partially regulate flooding in Kuala Lumpur. It offers flood storage up to the 100-year frequency of flood. The construction of the dam cost RM 20 million (excluding land purchase). Flood in the downstream communities has been decreased by activating Batu Dam and raising the level of water in the reservoir. In order to supply various areas of Kuala Lumpur with household and industrial water, Puncak Niaga is now abstracting water from the dam [15].
An earthfill main embankment, a spillway, and outlet work make up the project’s primary components. The dam is an earthfill embankment that is zoned [16]. A side-channel entrance structure with a crest works as the spillway. The outlet works are situated at the base of the left abutment to the right of the spillway structure. Water is delivered by the outflow works to the control structure’s municipal and industrial pipeline [15]. The combined spillway and outlet work total surcharge of 251.6 m3/s is offered as insurance against the likely maximum flood (PMF) and 234.2 m3/s of spillway capacities when outlet works is malfunction. Figure 1 shows the location of the dam in world map. Figure 2 displays an overview of Batu Dam and its components while Table 1 shows Batu Dam’s salient features.

2.2. Methods

2.2.1. Hydrological Analysis

  • Rainfall Time Series
Time-series analysis has evolved into an important technique in hydrology. It is used to construct synthetic hydrologic records, anticipate hydrologic occurrences, and discover patterns and shifts in hydrologic records [19].
2.
Double Mass Curve (DMC)
DMC is used to assess the regularity of various hydrologic data by assessing data from one station of interest to a pattern made of data from different stations in the region [20]. Due to its minimal data approach and high transferability, the DMC is frequently used for trend analysis [21]. Any DMC breakdowns may be the result of modifications made to the method of data collection or to physical modifications that have an effect on the relationship [20].
3.
Rainfall Temporal Pattern
For both rural and urban catchments, runoff routing methods or hydrologic models like unit hydrographs require rainfall temporal patterns in order to estimate floods [22]. In this study, the rainfall temporal pattern for Batu Dam catchment is available and published in Chapter 8 of Hydrological Procedures 1 (HP1) revised and updated 2015, which falls on Region 5–Urban Area (Kuala Lumpur) [23]. The patterns were available for 9 standard durations, 0.25, 0.5, 1, 3, 6, 12, 24, 48, and 72 h.
4.
Probable Maximum Precipitation (PMP)
PMP is “the highest depth of precipitation for a given duration meteorologically achievable for a given size storm area at a certain place at a particular time of year” [23,24]. For the catchment of a dam, hydrologists utilize a PMP magnitude together with its geographical and temporal distributions to determine the likely maximum flood (PMF). In the construction of hydrological structures, a variety of conceptual flood events are utilized, including the PMF. It is mostly used to design spillways that decrease the probability of a dam overtop [14].
Hershfield developed the statistical method that is used to calculate the PMP rainfall for a specific place or region using a general frequency equation they established [25,26] There are statistical techniques for estimating PMP that may be applied whenever there is enough precipitation data [27]. These methods are especially helpful when doing rapid estimations or when additional meteorological data such as wind records and dew point are absent [14]. The statistical approach developed by Hershfield is frequently employed today [7,8,9,10].
For stations with lengthy rainfall records, the Hershfield’s statistical methods are frequently employed to estimate PMP. If the data are not long enough to capture the excessive rainfall, PMP values may be underestimated [28]. Therefore, since the daily rainfall records are available for the study area, it is thus deemed appropriate to conduct a study on the approximation of PMP for hourly (1-, 3-, 6-, and 12-h and daily (1-, 2-, 3-, and 5-day) duration using the Hershfield approach using the following formula:
Xpmp = x ¯ n + Km σ n
where Km represents the frequency factor, σn is the series of standard deviations (SD), and x ¯ n is the mean of the annual maximum precipitation. In order to make the decision, it is necessary to obtain the mean and SD of the series for each station without taking into account the 10 years’ worth of highest precipitation, where
K m = ( X 1 x ¯ n 1 ) / σ n 1
Hershfield discovered that if an adequate envelope curve could be built based on the research area’s locations, it would yield accurate estimates of the PMP for different time periods of rainfall [12,28]. In 2008, National Hydraulic Research Institute Malaysia (NAHRIM) established an envelope curve for both in West and East Malaysia as a standard method of estimating PMP in Malaysia [14].
Figure 3 shows the Km envelope curve (west Malaysia), which is considered as an alternative method to calculate the Km frequency factor, which was developed by NAHRIM [14]. The PMP is computed using both Km frequency factors, and the most critical values from each approach are used as the input rainfall for the PMF simulation.

2.2.2. Hydrological Modeling

  • Probable Maximum Flood (PMF)
The flood that could be predicted from the most acute combination of adverse meteorological and hydrologic circumstances is known as the PMF [29]. The PMF is produced using the probable maximum precipitation (PMP) input data for this research area [27].
The Hydrologic Modeling System (HEC-HMS) software developed by USACE will be used to model the entire hydrologic process of branched watershed systems due to PMP to determine the PMF inflow of Batu Dam. For the HEC-HMS simulation, the required data are hydrological data, rainfall data, details of the dam, elevation-storage curve, and elevation-discharge curve. This model consists of several inputs such as basin model, meteorological model, control specification, time series data, and paired data as shown in Figure 4 [30]. Then, the deterministic steps for HEC-HMS simulation are illustrated in Figure 5 [29].
2.
Delineation of Subcatchment
The overall catchment area for Batu Dam is about 50 km2, which is then divided into six smaller subcatchments, namely S1–S6 characterized by different soil type and land use pattern delineated using GIS features in the HEC-HMS 4.8 model providing Digital Elevation Model (DEM) of ALOS PALSAR with resolution of 30 m in a coordinate system of Universal Transverse Mercator (UTM). The delineated six subcatchments are depicted in Figure 6.
All physical characteristics of the Batu Dam subcatchments such as the area of subcatchments, the longest flow path, elevation, and slope of the river can be obtained from the GIS features in HEC-HMS model after completing the delineation process, while study by the authors of [31] still used the ArcGIS tool to determine the physical parameter of the catchment for the input in the HEC-HMS model. All these physical characteristics then will be used to determine the input parameters by using the Malaysia guideline from [32] and calibrated by using guidelines from [33] as tabulated in Table 2.

3. Results and Discussion

3.1. Rainfall Time Series

For this study, four selected rainfall stations that fall within the Batu Dam catchment are used for the hydrological analysis which are Kg Sg Tua (3216001), Ibu Bekalan KM16 (3217001), Air Terjun Sg Batu (3317001), and Genting Sempah (3317004) as shown in Figure 7.
From the plotted daily rainfall time series (Figure 8), it can be observed that the highest recorded rainfall in station Kg Sg Tua (3216001) is 168.5 mm on 16 October 1976, Ibu Bekalan KM16 (3217001) with 158.5mm on 27 June 1994, Air Terjun Sg. Batu (3317001) with 204.0 mm on 1 February 2008, and Genting Sempah (3317004) with 128.4 mm on 31 May 2012.

3.2. Double Mass Curve

According to the plots (Figure 9), all four stations records show the consistency of data. The slope of all four mass curves with good consistency and quality as the slope value is close to 1 (Station No. 3216001: 0.99; Station No. 3217001: 0.99, Station No. 3317001: 1.03; and Station No. 3317004: 1.04).

3.3. Isohyet Map

Based on the hydrological analysis, maximum rainfall for (3-, 6-, and 12-h) and (1-, 2-, and 3-day) was acquired from the historical data up to the latest year. The interpolation method from GIS analysis has been carried out to create an Isohyet map for the studied catchment. The isohyet method was used to split the area based on the rain intensity, with contours functioning as dividing lines for the differences in rainfall intensity [34]. Figure 10 shows the maximum rainfall intensity of the Batu Dam catchment for different durations.
Based on Figure 10, the rainfall intensity for 3-h and (1, 2, and 3-day) durations are high at the center of the catchment which is located at the rainfall station of Air Terjun Sg Batu (3317001). Based on Google Earth, it can be observed that the location of this rainfall station is located in a thick rainforest while the location of the dam is located near to population downstream. The highest received rainfall in the Batu Dam catchment was in the range of 201mm to 220mm for (1, 2, and 3-day) durations, which are located at the middle upstream, can cause the increase of reservoir water level as it flows into the reservoir. Thus, dam monitoring during heavy rainfall event is very crucial for us to estimate the Rate of Rise (ROR) of the dam in case an emergency Action Plan (EAP) need to be activated.

3.4. Probable Maximum Precipitation (PMP)

Using the statistical approach, PMP is predicted for the following time periods: (1, 3, 6, and 12-h) and (1, 2, 3, and 5-day). Table 3 displays the projected PMP for Batu Dam for these periods using both statistical method by Hershfield’s and NAHRIM. By comparing both methods, it is found that PMP values using NAHRIM envelope curve gives higher value than Hershfield’s method. Thus, by considering worst case scenario, PMP values derived by using NAHRIM method will be adopted in this study to estimate the PMF.
The approach that gives the greatest PMP values is chosen as the most preferable method to be employed as rainfall inputs for PMF analyses. Previous studies by [35,36] also found that based on these two methods of PMP estimation between Hershfield’s method of derived Km and the NAHRIM Km envelope curve, the NAHRIM envelope curved is found to be the most reliable since it gives the higher estimation of PMP.

3.5. Probable Maximum Flood (PMF) and Dam Safety Check

By using the HEC-HMS model, PMF is then simulated for the duration of (1-, 3-, 6-, and 12-h) and (1-, 2-, 3-, and 5-day). Plotted results of PMF simulation at Batu Dam for various durations can be referred to in Figure 11. From Figure 11, it is found that the extreme flood of Batu Dam peaked at 3-h duration with PMF inflow of 522.7 m3/s.
The dam’s designed inflow value is compared with the highest PMF value for the Batu dam. It was discovered that the PMF of Batu Dam is 6.1% above the designed inflow values. Since the modified design flood is based on recent standards as required by ICOLD, and the inflow design is calculated using the Inflow Design Flood (IDF), the value is reasonable and expected. Additionally, the spillway capacity for the Batu dam is discovered to be sufficient to resist the peak flood PMF.
The PMF simulated spillway capacity for the Batu dam is 200.6 m3/s. It was found that these values are 14.4% lower in comparison to the designed spillway capacities. The simulated reservoir level also found to be 0.6 m lower than the designed level. Table 4 compares the designed inflow and revised PMF for the Batu dam along with the designed spillway capacities and the simulated reservoir level.
Even though the inflow of PMF is higher than the design inflow, the design spillway capacity still can cater the revised spillway discharge. The simulated reservoir level is lower than the reservoir level obtained from designed inflow, implying that the simulated inflow volume from PMF in this study is lesser than the designed inflow volume. The discrepancy may be due to different initial dam condition boundary including adopted elevation-storage curve during the design stage and current simulation resulting in lower peak discharge compared to design capacities. It can be concluded that the existing spillway still can cater to the estimated inflow due to PMF which reduces the probability of overtopping with freeboard of 1.6 m from the dam crest.

4. Conclusions

Since the statistical method of estimating PMP require real historical rainfall data in the study area, hydrological analysis including rainfall time series and double mass curve allow us to discover the patterns of the historical rainfall data and reliability of the record. Computation of PMP and PMF are important in dam safety as it can be a simple safety check and suggestions on future dam failure criteria especially in hydrological type of failure mode. By comparing both statistical methods of computing PMP values by Hershfield’s derived Km and using the recent NAHRIM published envelope curve, it can be observed that PMP values by using the NAHRIM envelope curve are higher than the Hershfield’s derived Km method, which then has been adopted as input for the hydrological modeling to estimate the PMF. This finding seems to be concurrent with the statement by Hershfield [12,37] as if an envelope curve can be built based on the study area, it would yield accurate estimation of the PMP values. An established hydrologic modeling software by USACE, which is HEC-HMS, is then used to estimate the PMF value for Batu Dam as well as the simulated spillway discharge due to PMF inflow. The estimated PMF for the Batu dam is found to exceed the capacities of the design inflow. Nevertheless, under PMF conditions, the Batu dam will not face overtopping since the simulated reservoir level is still below the crest level of the dam. The spillway capacities of the Batu dam also seem to be adequate with the design capacities of 200.6 m3/s. Therefore, it is suggested to allocate additional facilities such as rainfall stations at the upstream catchment to observe the inflow into the catchment and streamflow stations at the downstream to observe the outflow of the catchment. It is also recommended to implement Risk Informed Decision Making (RIDM) for the Batu dam as a tool for dam safety assessment to minimize the impact of dam failure located in an urban area.

Author Contributions

Conceptualization, L.M.S. and H.B.; Formal analysis, S.M.A.O. and W.N.H.W.A.; Funding acquisition, L.M.S.; Investigation, S.M.A.O. and W.N.H.W.A.; Methodology, S.M.A.O., L.M.S. and H.B.; Project administration, M.H.M.K.; Resources, H.B.; Software, S.M.A.O.; Supervision, L.M.S. and H.B.; Validation, L.M.S. and H.B.; Writing—original draft, S.M.A.O.; Writing—review & editing, S.M.A.O., L.M.S., H.B. and A.N.A. All authors have read and agreed to the published version of the manuscript.

Funding

This research was funded by the Ministry of Higher Education (MoHE), Malaysia, grant number TRGS/1/2020/UNITEN/01/1/1. The research also received financial support from Universiti Tenaga Nasional (UNITEN) grant number J510050002-IC-6 BOLDREFRESH2025.

Institutional Review Board Statement

Not applicable.

Informed Consent Statement

Not applicable.

Data Availability Statement

The data adopted in this study are available at the National Hydrological Network Management System (SPRHiN). Any interested person(s) could get it from the website at http://sprhin.water.gov.my/bin/borang/login.cfm (accessed on 18 May 2022).

Acknowledgments

The authors acknowledge the Ministry of Higher Education (MoHE), Malaysia, for the financial support through the Trans-Disciplinary Research Grant (TRGS). The authors would like also to acknowledge the BOLD Refresh Grant. Additionally, we would like to express our gratitude to the Malaysian Universiti Tenaga Nasional (UNITEN) and its Institute of Energy and Infrastructure (IEI) for its support of this project. The Department of Irrigation and Drainage (DID) deserves special gratitude for its contribution to provide the data needed for this study.

Conflicts of Interest

The authors declare no conflict of interest.

References

  1. Gebregiorgis, A.S.; Hossain, F. Hydrological Risk Assessment of Old Dams: Case Study on Wilson Dam of Tennessee River Basin. J. Hydrol. Eng. 2012, 17, 201–212. [Google Scholar] [CrossRef] [Green Version]
  2. Gabriel-Martin, I.; Sordo-Ward, A.; Garrote, L.; Granados, I. Hydrological risk analysis of dams: The influence of initial reservoir level conditions. Water 2019, 11, 461. [Google Scholar] [CrossRef] [Green Version]
  3. Norouzi, N. Climate change impacts on the water flow to the reservoir of the Dez Dam basin. Water Cycle 2020, 1, 113–120. [Google Scholar] [CrossRef]
  4. Raudkivi, A.J. Hydrology: An Advanced Introduction to Hydrological Processess and Modelling; Elsevier: Amsterdam, The Netherlands, 2013. [Google Scholar]
  5. Goodarzi, E.; Shui, L.T.; Ziaei, M. Dam overtopping risk using probabilistic concepts-Case study: The Meijaran Dam, Iran. Ain Shams Eng. J. 2013, 4, 185–197. [Google Scholar] [CrossRef] [Green Version]
  6. Tingsanchali, T.; Tanmanee, S. Assessment of hydrological safety of Mae Sruai Dam, Thailand. Procedia Eng. 2012, 32, 1198–1204. [Google Scholar] [CrossRef] [Green Version]
  7. Singh, A.; Singh, V.P.; Ar, B. Computation of probable maximum precipitation and its uncertainty. Int. J. Hydrol. 2018, 2, 504–514. [Google Scholar] [CrossRef] [Green Version]
  8. Suribabu, C.R. An alternate method for finding Probable Maximum Precipitation (PMP) for Indian monsoon precipitation. ISH J. Hydraul. Eng. 2021, 27, 371–375. [Google Scholar] [CrossRef]
  9. Koutsoyiannis, D. A probabilistic view of Hershfield’s method for estimating probable maximum precipitation. Water Resour. Res. 1999, 35, 1313–1322. [Google Scholar] [CrossRef]
  10. Lave, L.B.; Balvanyos, T. Risk analysis and management of dam safety. Risk Anal. 1998, 18, 455–462. [Google Scholar] [CrossRef]
  11. Liu, Z.; Xu, X.; Cheng, J.; Wen, T.; Niu, J. Hydrological risk analysis of dam overtopping using bivariate statistical approach: A case study from Geheyan Reservoir, China. Stoch. Environ. Res. Risk Assess. 2018, 32, 2515–2525. [Google Scholar] [CrossRef]
  12. Hershfield, D.M. Estimating the Probable Maximum Precipitation. J. Hydraul. Div. 1961, 87, 99–106. [Google Scholar] [CrossRef]
  13. Hershfield, D.M. Method for Estimating Probable Maximum Precipitation. J. Am. Water Work. Assoc. 1965, 57, 965–972. [Google Scholar] [CrossRef]
  14. National Hydraulic Research Institute of Malaysia (NAHRIM). Derivation of Probable Maximum Precipitation for Design Floods in Malaysia, NAHRIM Technical Research Publication No. 1 (TRP 1); No. 1; NAHRIM: Seri Kembangan, Malaysia, 2008; Volume 1.
  15. Department of Irrigation and Drainage (DID). Batu Dam. 2017. Available online: https://www.water.gov.my/index.php/pages/view/1241 (accessed on 9 August 2021).
  16. Suratman, S. Geology and related activities in the construction of Batu Dam, Kuala Lumpur. Bull. Geol. Soc. Malays. 1994, 35, 15–23. [Google Scholar] [CrossRef] [Green Version]
  17. Ali Benzaghta, M. Prediction of evaporation in tropical climate using artificial neural network and climate based models. Sci. Res. Essays 2012, 7, 3133–3148. [Google Scholar] [CrossRef]
  18. Desa, M.N.M.; Noriah, A.; Rakhecha, P. Probable maximum precipitation for 24h duration over southeast Asian monsoon region—Selangor, Malaysia. Atmos. Res. 2001, 58, 41–54. [Google Scholar] [CrossRef]
  19. Naill, P.E.; Momani, M. Time Series Analysis Model for Rainfall Data in Jordan: Case Study for Using Time Series Analysis. Am. J. Environ. Sci. 2009, 5, 599–604. Available online: http://www.thescipub.com/abstract/?doi=ajessp.2009.599.604 (accessed on 7 September 2022).
  20. Searcy, J.K.; Hardison, C.H. Double Mass Curves—Manual of Hydrology: Part 1. General Surface-Water Techniques; Issue 1541, U.S. Government Printing Office: Washington, DC, USA, 1960.
  21. Gao, P.; Li, P.; Zhao, B.; Xu, R.; Zhao, G.; Sun, W.; Mu, X. Use of double mass curves in hydrologic benefit evaluations. Hydrol. Process. 2017, 31, 4639–4646. [Google Scholar] [CrossRef]
  22. Hong, J.L.; Jafri, A.; Ibrahim, I.; Shafie, S.; Hong, K.A.; Naubi, I. Design Rainfall Temporal Patterns for Upper Klang Catchment. J. Inst. Eng. Malays. 2018, 79, 21–30. [Google Scholar] [CrossRef]
  23. Department of Irrigation and Drainage (DID). Hydrological Procedure No. 1 (Revised and Updated 2015) Estimation of Design Rainstorm in Peninsular Malaysia; No. 1; DID: Kuala Lumpur, Malaysia, 2015; Volume 1.
  24. Hansen, E.M.; Schreiner, L.C.; Miller, J.F. Hydrometeorological Report 52 Application of Probable Maximum Precipitation Estimates—United States East of the 105th Meridian; U.S. Department of Commerce: Washington, DC, USA, 1982.
  25. WMO. Operational Hydrology Report No. 1: Manual for Estimation of Probable Maximum Precipitation; WMO: Geneva, Switzerland, 1986. [Google Scholar]
  26. Te Chow, V. A General Formula for Hydrologic Frequency Analysis. Trans. Am. Geophys. Union 1951, 32, 231–237. [Google Scholar] [CrossRef]
  27. Durbude, D.G. Estimation of Probable Maximum Precipitation for Planning of Soil and Water Conservation Structures. J. Water Conserv. 2008, 7, 31–35. [Google Scholar]
  28. Deshpande, N.R.; Kulkarni, B.D.; Verma, A.K.; Mandal, B.N. Extreme rainfall analysis and estimation of probable maximum precipitation (PMP) by statistical methods over the Indus river basin in India. J. Spat. Hydrol. 2008, 8, 22–35. [Google Scholar]
  29. Lariyah, M.S.; Faizah, C.R.; Mohd Noh, A.; Rahsidi, S.M.; Azwin Zailti, A.R.; Mohd Nor, M.D.; Hidayah, B.; Intan Shafilah, A.A. Development of Probable Maximum Flood (PMF) for Sultan Abu Bakar Dam. In Proceedings of the EnCon 2012, 5th Engineering Conference, “Engineering Towards Change—Empowering Green Solutions”, Kuching Sarawak, Malaysia, 10–12 July 2012. [Google Scholar]
  30. Fleming, M.J. Hydrologic Modeling System Quick Start Guide; US Army Corps of Engineers; Hydrologic Engineering Center: Davis, CA, USA, 2013; p. 52.
  31. Boota, M.W.; Nabi, G.; Abbas, T.; Yaseen, M.; Faisal, M.; Azam, M.I. Estimation of Probable Maximum Flood (PMF): A Case Study of Pothwar Region, Pakistan. Int. J. Sci. Res. Eng. Dev. 2015, 2, 6471–6475. Available online: http://www.sci-int.com/pdf/636339897657542910.pdf (accessed on 7 September 2022).
  32. Department of Irrigation and Drainage (DID). Hydrological Procedure No. 27: Estimation of Design Flood Hydrograph Using Clark Method for Rural Catchments in Peninsular Malaysia; No. 27; DID: Kuala Lumpur, Malaysia, 2010.
  33. Department of Irrigation and Drainage (DID). Hydrological Procedure No. 11: Design Flood Hydrograph Estimation for Rural Cachments in Malaysia; DID: Kuala Lumpur, Malaysia, 2018.
  34. Nur, H.S.; Mohd, K.; Mohd, E.T.; Hafizan, J.; Ata, F.M.; Azman, A.; Noor Jima, A.W.; Umar, R.; Khalit, S.I.; Makhtar, M. Relationship of rainfall distribution and water level on major flood 2014 in Pahang River Basin, Malaysia. Environ. Asia 2017, 10, 1–8. [Google Scholar]
  35. Yiau, S.S.; Putuhena, F.J. Probable Maximum Precipitation (PMP) Analysis for Bakun Dam Area. J. Civ. Eng. Sci. Technol. 2011, 2, 53–59. [Google Scholar]
  36. Razali, J.; Sidek, L.M.; Rashid, M.A.; Hussein, A.; Marufuzzaman, M. Probable Maximum Precipitation comparison using hershfield’s statistical method and hydro-meteorological method for Sungai Perak Hydroelectric Scheme. Int. J. Eng. Technol. 2018, 7, 603–608. [Google Scholar] [CrossRef]
  37. Sammen, S.; Mohamed, T.; Ghazali, A.A.; Sideq, L.; Aziz, A.A. Estimation of probable maximum precipitation for tropical catchment. MATEC Web Conf. 2018, 162, 1–5. [Google Scholar] [CrossRef]
Figure 1. Location of Batu Dam, Malaysia in World Map.
Figure 1. Location of Batu Dam, Malaysia in World Map.
Ijerph 19 16530 g001
Figure 2. Components of Batu Dam.
Figure 2. Components of Batu Dam.
Ijerph 19 16530 g002
Figure 3. The Km envelope curve (West Malaysia) [14].
Figure 3. The Km envelope curve (West Malaysia) [14].
Ijerph 19 16530 g003
Figure 4. HEC-HMS Input.
Figure 4. HEC-HMS Input.
Ijerph 19 16530 g004
Figure 5. Steps for HEC-HMS simulation.
Figure 5. Steps for HEC-HMS simulation.
Ijerph 19 16530 g005
Figure 6. Basin Model Setup for Batu Dam Scheme.
Figure 6. Basin Model Setup for Batu Dam Scheme.
Ijerph 19 16530 g006
Figure 7. Rainfall stations within the Batu Dam catchment.
Figure 7. Rainfall stations within the Batu Dam catchment.
Ijerph 19 16530 g007
Figure 8. Daily rainfall time series of the station (a) Kg Sg Tua (3216001), (b) Ibu Bekalan KM16 (3217001), (c) Air Terjun Sg Batu (3317001), and (d) Genting Sempah (3317004).
Figure 8. Daily rainfall time series of the station (a) Kg Sg Tua (3216001), (b) Ibu Bekalan KM16 (3217001), (c) Air Terjun Sg Batu (3317001), and (d) Genting Sempah (3317004).
Ijerph 19 16530 g008
Figure 9. Double mass curve of the station (a) Kg Sg Tua (3216001), (b) Ibu Bekalan KM16 (3217001), (c) Air Terjun Sg Batu (3317001), and (d) Genting Sempah (3317004).
Figure 9. Double mass curve of the station (a) Kg Sg Tua (3216001), (b) Ibu Bekalan KM16 (3217001), (c) Air Terjun Sg Batu (3317001), and (d) Genting Sempah (3317004).
Ijerph 19 16530 g009
Figure 10. Isohyets Map for the recorded rainfall (extreme events) in mm different durations.
Figure 10. Isohyets Map for the recorded rainfall (extreme events) in mm different durations.
Ijerph 19 16530 g010
Figure 11. PMF simulations at Batu dam.
Figure 11. PMF simulations at Batu dam.
Ijerph 19 16530 g011
Table 1. Salient features of Batu Dam.
Table 1. Salient features of Batu Dam.
BATU DAM
FunctionWater supply for both municipal and industrial, sediment control, and flood control
Direct Catchment Area50 km2
Surface Area at Maximum FSL2.5 km2
Normal Pool LevelEl. 102.7 m
Full Supply LevelEL 107.3 m
RESERVOIR
Storage Capacity36.6 Mm3
Peak inflow design flood (IDF)492.7 m3/s
Design Discharge Capacities251.6/s (spillway and outlet)
234.2 m3/s (spillway only)
DAM
TypeEarthfill
Height 44 m
Length550 m
Crest Elevation (m)El. 109.0 m
SPILLWAY
Crest ElevationEl. 104.85 m
Invert ElevationEl. 97.83 m at upstream
Crest Length23 m
Total length226.53 m to the stilling basin
Table 2. Input Parameter of HEC-HMS.
Table 2. Input Parameter of HEC-HMS.
Sub-BasinLoss MethodTransform MethodBaseflow Method
Initial and ConstantClark (UH)Constant Monthly
Initial Loss (mm)Constant Rate (mm/h)Imperviousness (%)SCS Tc Eq. (h)R (h) HP27HP 27
(m3/s)
S1302.5103.111.2180.905
S2302.5102.661.1160.584
S3302.5102.180.8390.496
S4302.5106.032.2621.073
S5302.5104.681.9570.597
S6302.5103.001.2790.449
Table 3. Probable maximum precipitation (PMP) estimation of Batu dam.
Table 3. Probable maximum precipitation (PMP) estimation of Batu dam.
MethodPMP in mm for Various Durations
1-h3-h6-h12-h1-Day2-Day3-Day5-Day
Statistical–Hershfield’s Method
(Derived Km)
104.38182.62197.26187.02215.68305.63329.90437.27
Statistical–NAHRIM Method
(Km Envelope Curve)
179.31261.91280.43309.01398.42549.59557.78613.27
Table 4. Designed inflow and designed discharge capacities based on PMF values.
Table 4. Designed inflow and designed discharge capacities based on PMF values.
DamDesigned Inflow (m3/s)PMF (m3/s)Designed Discharge Capacities (m3/s)Revised Spillway Capacities (m3/s)Reservoir Level for Designed
Inflow (m)
Simulated
Reservoir Level (m)
Batu492.7522.7234.2200.6108.0107.4
Publisher’s Note: MDPI stays neutral with regard to jurisdictional claims in published maps and institutional affiliations.

Share and Cite

MDPI and ACS Style

Allias Omar, S.M.; Wan Ariffin, W.N.H.; Mohd Sidek, L.; Basri, H.; Moh Khambali, M.H.; Ahmed, A.N. Hydrological Analysis of Batu Dam, Malaysia in the Urban Area: Flood and Failure Analysis Preparing for Climate Change. Int. J. Environ. Res. Public Health 2022, 19, 16530. https://doi.org/10.3390/ijerph192416530

AMA Style

Allias Omar SM, Wan Ariffin WNH, Mohd Sidek L, Basri H, Moh Khambali MH, Ahmed AN. Hydrological Analysis of Batu Dam, Malaysia in the Urban Area: Flood and Failure Analysis Preparing for Climate Change. International Journal of Environmental Research and Public Health. 2022; 19(24):16530. https://doi.org/10.3390/ijerph192416530

Chicago/Turabian Style

Allias Omar, Siti Mariam, Wan Noorul Hafilah Wan Ariffin, Lariyah Mohd Sidek, Hidayah Basri, Mohd Hazri Moh Khambali, and Ali Najah Ahmed. 2022. "Hydrological Analysis of Batu Dam, Malaysia in the Urban Area: Flood and Failure Analysis Preparing for Climate Change" International Journal of Environmental Research and Public Health 19, no. 24: 16530. https://doi.org/10.3390/ijerph192416530

Note that from the first issue of 2016, this journal uses article numbers instead of page numbers. See further details here.

Article Metrics

Back to TopTop