Quantifying BIM investment value: a systematic review

Lina Gharaibeh (Department of Engineering Science, University West, Trollhättan, Sweden)
Kristina Eriksson (Department of Engineering Science, University West, Trollhättan, Sweden)
Björn Lantz (Department of Engineering Science, University West, Trollhättan, Sweden)

Journal of Engineering, Design and Technology

ISSN: 1726-0531

Article publication date: 13 March 2024

307

Abstract

Purpose

Perceived benefits of building information modelling (BIM) have been discussed for some time, but cost–benefit benchmarking has been inconsistent. The purpose of this paper is to investigate BIM feasibility and evaluate investment worth to elucidate and develop the current understanding of BIM merit. The aim of the study is to propose a research agenda towards a more holistic perspective of BIM use incorporating quantifying investment return.

Design/methodology/approach

An in-depth examination of research patterns has been conducted to identify challenges in the assessment of the investment value and return on investment (ROI) for BIM in the construction industry. A total of 75 research articles were considered for the final literature review. An evaluation of the literature is conducted using a combination of bibliometric analysis and systematic reviews.

Findings

This study, which analysed 75 articles, unveils key findings in quantifying BIM benefits, primarily through ROI calculation. Two major research gaps are identified: the absence of a standardized BIM ROI method and insufficient exploration of intangible benefits. Research focus varies across phases, emphasizing design and construction integration and exploring post-construction phases. The study categorizes quantifiable factors, including productivity, changes and rework reduction, requests for information reduction, schedule efficiency, safety, environmental sustainability and operations and facility management. These findings offer vital insights for researchers and practitioners, enhancing understanding of ’BIM’s financial benefits and signalling areas for further exploration in construction.

Originality/value

The ’study’s outcomes offer the latest insights for researchers and practitioners to create effective approaches for quantifying ’BIM’s financial benefits. Additionally, the proposed research agenda aims to improve the current limited understanding of BIM feasibility and investment worth evaluation. Results of the study could assist practitioners in overcoming limitations associated with BIM investment and economic evaluations in the construction industry.

Keywords

Citation

Gharaibeh, L., Eriksson, K. and Lantz, B. (2024), "Quantifying BIM investment value: a systematic review", Journal of Engineering, Design and Technology, Vol. ahead-of-print No. ahead-of-print. https://doi.org/10.1108/JEDT-06-2023-0259

Publisher

:

Emerald Publishing Limited

Copyright © 2024, Lina Gharaibeh, Kristina Eriksson and Björn Lantz.

License

Published in Asia Pacific Journal of Innovation and Entrepreneurship. Published by Emerald Publishing Limited. This article is published under the Creative Commons Attribution (CC BY 4.0) licence. Anyone may reproduce, distribute, translate and create derivative works of this article (for both commercial and non-commercial purposes), subject to full attribution to the original publication and authors. The full terms of this licence may be seen at http://creativecommons.org/licences/by/4.0/legalcode


1. Introduction

Building information modelling (BIM) is defined as the process of representing the physical and functional elements of a building digitally (Lee and Lee, 2020; Primasetra et al., 2022). BIM creates a transparent environment that enables all project stakeholders to interact in a transparent manner by integrating multidisciplinary project teams into a shared platform (Hussain et al., 2023). According to the architecture, engineering and construction industry, BIM refers to a design management methodology that links all phases of construction projects through the use of three-dimensional (3D) models (Condotta and Scanagatta, 2023; Hasanain and Nawari, 2022). As part of the BIM-based project management process, a 3D model is created which contains information on the geometric and non-geometric attributes of the building, as well as digital replicas of products from the manufacturer (Li et al., 2023). Data are gathered into a shared data environment in which all project information is kept up-to-date and communicated to stakeholders in order to ensure the highest level of resource efficiency throughout the project life cycle (Feng et al., 2023; Lu et al., 2023).

BIM serves a multifaceted role encompassing visualization, cost estimation, scheduling, clash detection and collaborative data coordination, driven by its parametric capabilities (Khanzode et al., 2008; Krystallis et al., 2019; Love et al., 2013). As a solution to address fragmentation, complexity and high-risk challenges within the construction supply chain, researchers advocate for BIM adoption (Sánchez et al., 2022; Zakeri et al., 2023). Given the intricate nature of construction projects involving numerous stakeholders, uninterrupted material flow, concurrent activities at shared locations and extensive interdisciplinary coordination, ’BIM’s significance is paramount (Kim et al., 2020; Qian, 2012). The burgeoning attention towards BIM utilization is underscored by its proponents who extol its advantages, urging the industry to enhance its implementation efforts (Harris et al., 2015; Sompolgrunk et al., 2023). The ’industry’s adoption of BIM is profoundly influenced by its recognition of the ’technology’s financial benefits (Sánchez et al., 2022). Demonstrating the value of a novel technology or business model to organizational decision-makers is a pivotal strategy for its promotion, making the quantification of ’BIM’s value increasingly significant (Ardani et al., 2022; Lee and Lee, 2020).

Having a thorough understanding of the business benefits of BIM can assist organizations in making informed decisions about whether to invest in BIM technology and how to implement it effectively (Ardani et al., 2022; Cucuzza et al., 2022; Gharaibeh et al., 2022). An organization can evaluate the potential return on investment (ROI) and determine whether the benefits outweigh the costs by identifying the specific benefits that BIM can provide, such as cost savings, improved productivity and reduced errors. Further, a thorough understanding of ’BIM’s business benefits will help organizations formulate a well-defined strategy for implementing BIM and maximizing its benefits (Azhar, 2011; Harris et al., 2015). For example, if reducing construction errors is the primary objective, then BIM can be used to detect and coordinate clashes (Daszczyński et al., 2022). Furthermore, if the organization is focused on reducing project costs, it may prioritize the use of BIM for material optimization and pre-fabrication (Yu et al., 2022).

The industry may find it challenging to determine the investment value of BIM within their own organization owing to a number of factors (Ardani et al., 2022; Qian, 2012). Currently, there is no standardized way to measure the benefits of BIM, and different organizations may define success differently (Lee and Lee, 2020). Further, evaluating the financial impact of BIM can be challenging, especially for smaller projects or those that have been completed over a long period of time (Kim et al., 2022; Xenidis and Koukoulis, 2022). In addition to being a complex technology, ’BIM’s benefits can be difficult to quantify, and there is also often a resistance to change (Love et al., 2013). Even though perceived benefits using BIM have been discussed for quite some time, no consistent, cost–benefit benchmarking has been conducted. It is imperative that building industry professionals have access to cost–benefit information to take the step towards adopting BIM in accordance with their own internal strategies and innovation plans.

The purpose of the literature review presented in this paper is to conduct a comprehensive investigation into the feasibility of BIM and to assess its investment value. Through this endeavour, the research seeks to elucidate and enhance the existing knowledge regarding the merits of BIM adoption within the construction industry. The overarching aim of this study is to propose a research agenda that fosters a more comprehensive understanding of ’BIM’s feasibility, encompassing the quantitative assessment of its ROI.

2. Tangible and intangible effects of BIM

BIM impacts cannot be accurately translated into numerical values owing to several limitations (PWC, 2018). Measurement of BIM effects is based on various assumptions as compared to a situation in which it is not used (Sheikhkhoshkar et al., 2018). This is evident is several previous publications in which an attempt to report numerical values for the BIM investment worth were made (Ardani et al., 2022; Latiffi and Tai, 2017; Qian, 2012). However, these studies did not provide detailed descriptions of the assumptions and calculation processes used to derive these values. There is a wide range of numerical values reported in these cases; therefore, these results question the reliability of BIM applications and lead to a negative perception of them (Sánchez et al., 2022). Another limitation of previous BIM investment evaluation studies is that it is difficult to propose a comprehensive BIM assessment methodology that considers all possible effects (Barlish and Sullivan, 2012; Tu et al., 2023). In construction projects, BIM creates a variety of effects, and an integrated BIM evaluation should take all possible effects into consideration (Zakeri et al., 2023). To determine the investment worth of BIM, effects must be converted into costs (Toan et al., 2022). However, converting all of these effects into costs is virtually impossible (Krystallis et al., 2019). Thus, any methodology that considers only the tangible effects that can be converted to costs suggests that the results are unreasonable or limited (PWC, 2018).

BIM benefits calculations face significant challenges as intangible effects, such as improving communication between participants, are difficult to convert into costs (Ardani et al., 2022). In contrast to intangible effects resulting from BIM adoption, many previous studies focused on tangible effects as preventing rework, or reducing time, which are easily converted into costs (Lee et al., 2018; Yu et al., 2022). Measuring the intangible benefits of BIM can be challenging for several reasons (Primasetra et al., 2022). These reasons include the lack of standardized metrics (Sheikhkhoshkar et al., 2018), subjectivity (Kim et al., 2020), the time frame required to evaluate these benefits (Zhang et al., 2022) and the complexity of BIM (Condotta and Scanagatta, 2023). In addition, the subjective nature of these benefits and the difficulty of attributing them directly to the technology further complicates the process (Hosseini et al., 2016). Intangible benefits include improved collaboration, better decision-making and improved project outcomes (Hussain et al., 2023; Kineber et al., 2023). These benefits may not have an obvious money value, making it difficult to measure their impact (PWC, 2018). Despite these challenges, understanding and measuring intangible benefits is crucial to gaining a comprehensive understanding of the overall impact of BIM on a project or organization (Ham et al., 2018).

It is also vital that the industry acknowledges that the investment of BIM is a long-term investment, meaning that ’BIM’s value proposition extends beyond the static benefits realized during a single project (Primasetra et al., 2022; Zhao et al., 2022). A BIM-driven project will provide valuable knowledge and experience that can be applied to almost all future projects (Kim et al., 2020). In addition, value runs along the complete life cycle of a construction project, which includes the design, construction, operation and maintenance of the facility (Feng et al., 2023; Toan et al., 2022). It is possible though that there may not be sufficient data to measure or elaborate on the life cycle benefits of BIM since the projects that have used it are relatively recent (Hussain et al., 2023). Additionally, ’BIM’s true value can only be determined once all downstream activities have been considered (Motalebi et al., 2022). The calculation of ROI and cost–benefit analysis (CBA) may prove to be quite a challenge when considering all aspects of construction from conception to demolition, and hence, several research studies focused on evaluating the benefits of a certain aspect solely to avoid the complexity of the overall life cycle (Hwang and Zhao, 2018; Sabbaghzadeh et al., 2022; Won et al., 2016).

A review of the existing literature indicates that there is no agreement on a methodology for calculating the true investment value of BIM. The broader and more in-depth examination of previous work in this area revealed that the economic impact of BIM is little known, apart from some general allegations that have been made in academic and industry resources. The existing and proposed methodologies may not be formulated in a way that will aid industrial organizations in assessing the perceived value of BIM tailored to their specific operations. As a result of examining the existing literature, several methodologies focused solely on specific attributes or specific cases or projects, but there is a lack of a comprehensive cost–benefit model that can measure the ROI of BIM throughout the entire construction supply chain life cycle. Hence, this study seeks to summarize the current state-of-the-art for capturing BIM investment value by conducting a bibliometric systematic literature review (SLR) to gather and align all methodologies available in the literature. It is anticipated that the results will assist in guiding a more targeted approach towards efforts to close the research gaps that remain in the calculations of BIM feasibility and ROI.

3. Systematic literature review

An in-depth and detailed examination of research patterns has been conducted to identify challenges in the assessment of the investment value and ROI for BIM in the construction industry. An evaluation of the literature is conducted using a combination of bibliometric analysis (quantitative research) and systematic reviews (qualitative research). In the context of an integrated review approach, conclusions derived from both quantitative and qualitative methods may be consolidated and validated, providing persuasive results in the event of discrepancies or contradictions between them (Kitchenham, 2004). Further, using this hybrid review approach provides the opportunity to examine research from a variety of perspectives, thus increasing the scope and depth of the conclusions derived from the review (Okoli, 2015).

An SLR is a methodical approach used to collect, analyse and summarize existing research pertaining to a specific topic or research question (Nightingale, 2009). Its goal is to offer a comprehensive understanding of the existing evidence and pinpoint areas where knowledge gaps exist. In this study, we use SLR to explore the current state-of-the-art in assessing the value of BIM investments and the methodologies used to quantify their benefits. The research follows a systematic methodology as described in Figure 1.

3.1 Defining the research questions

The research strategy was initiated by identifying the research questions; the objective of the research is to summarize the current state-of-the-art for capturing BIM investment value by conducting an SLR to gather and align all methodologies available in the literature. The remaining of the research is directed towards answering three research questions as follows:

RQ1.

What are the methods used to quantify BIM benefits?

RQ2.

What are the quantifiable factors that can be used to evaluate the investment value of BIM?

RQ3.

What are the current research gaps in BIM benefits quantification?

3.2 Data collection

Acquiring studies pertinent to the topic of this research was crucial, specifically utilizing bibliometric analysis to develop a quantitative understanding of the knowledge domain. The first step in collecting the relevant literature was to identify relevant databases. Compared to Web of Science and other databases, Scopus has more publications and quicker updates. Scopus was therefore selected as the source for literature search in this study. The keywords used are shown in Table 1, and since the literature covers a wide range of aspects and metrics spanning the entire project life cycle, a single keyword search was not adequate. Several iterations using different keyword selections were used to ensure the findings were adequate. Results were screened and refined based on title, source, language and relevance after each keyword search.

3.3 Inclusion criteria and quality assurance

The articles selected for this review encompassed relevant publications from the past two decades, with a particular emphasis on the utilization of diverse assessment methodologies found in the literature. The chosen publication date range was deemed appropriate, given the well-established and enduring nature of economic methodologies. The review was confined to articles published in the English language.

To maintain consistency and ensure a high standard of review, we followed the customary practice of including only journal articles in our literature review, as recommended by Sompolgrunk et al. (2022). Journal articles, which typically present comprehensive and self-contained research findings, undergo multiple rounds of rigorous peer review. In contrast, conference papers often showcase preliminary research findings and may signify ongoing work to achieve specific research objectives. Although conference papers generally provide valuable insights, we made exceptions by including conference papers from reputable conferences that use a peer review process, following a manual quality assessment.

Consequently, most of the references cited in this paper originate from peer-reviewed publications featured in prominent international journals and conferences, known for their adherence to high standards of quality and rigor. Additionally, our review incorporates reports and case studies released by industry leaders and multinational corporations recognized for their excellence in research and innovation.

A total of 75 research articles were considered for the final literature review. A standardized data extraction form to record relevant information was made. From each article, both quantitative and qualitative data were recorded such as, title, year, source, method, attribute, project phase and the type of results reported.

4. Results

Figure 2 provides a visual representation of the distribution of the selected articles over the years. The search parameters encompassed articles published from year 2000 to the present day. The articles ultimately included in the study span the years from 2004 to 2023. It is worth noting that, at the time of this search, 14 articles scheduled for publication in 2023 were also incorporated into the analysis following a final screening process.

This distribution pattern underscores the relatively recent emergence of interest in assessing the investment value of BIM. The trend depicted in the figure reflects an ongoing and expanding interest in this area of research, indicating its growing significance in contemporary discussions within the field.

Table 2 summarizes the classification of the reviewed literature; 72% of the sources were journal articles. The table mentions the journals in which several relevant publications were found, such as Automation in Construction had eight articles published on the topic of quantifying the benefits of BIM, whereas Sustainability, Journal of Construction Engineering and Management and Journal of Civil Engineering and Management had five, four and three articles, respectively. Eighteen percent of the reviewed articles were published in conference proceedings. As mentioned earlier, the conference articles were scrutinized to ensure presence of quality results. Seven other sources were included and were found to have essential content contributing to the subject, such as industry reports and case analysis that were performed as part of industrial research.

In prior literature, a consensus exists that BIM investment yields both tangible and intangible benefits and costs. This study encompasses all relevant research efforts that aim to quantify or understand the value associated with these tangible and intangible metrics. Therefore, it is imperative to scrutinize the research methodologies used in exploring the investment value of BIM to gain insight into past research trends. Figure 3 visually represents the methods used in the literature under analysis.

Additionally, the analysis examined the focus of the research according to the project phase. While quantifying the benefits and costs associated with adopting BIM technology allows for a more comprehensive understanding of both the benefits and costs associated with this technology, several studies have focused on a particular part of a project’s life cycle to generate more significant results. Figure 4 illustrates the distribution of the analysed articles along the project life cycle.

Figure 5 summarizes the extracted quantifiable results from the analysed articles and lists the values that were identified in the literature for each attribute or factor. Content analysis of each of the attributes is presented in the discussion section to provide more context of the derived conclusion.

5. Discussion

The remainder of the research is dedicated to addressing the research questions that have been identified, drawing upon the outcomes derived from the SLR analysis. Each research query is methodically answered and elaborated upon, taking into consideration the findings presented in the results section, and supplemented by a qualitative content analysis of the pertinent articles:

RQ1.

What are the methods used to quantify BIM benefits?

As shown in Figure 3, several research methods were used in previous studies to quantify BIM benefits. A case study analysis was, not unexpectedly, the most commonly used method, as actual case studies are the most accurate method to obtain real values from construction projects in real life (Kim et al., 2022). The analysis revealed that it is widely accepted that case studies are a popular method for quantifying the impact of BIM, due to their real-world context, in-depth analysis, insights into customization and ability to evaluate outcomes. Researchers and practitioners can better understand and optimize BIM implementation in the construction industry by using case studies that focus on individual projects and integrate rich data sources.

Researchers commonly use surveys and interviews to collect firsthand insights from professionals engaged in BIM implementation. Combining case studies with surveys and interviews enhances researchers’ comprehension of ’BIM’s influence, enabling them to incorporate both practical experiences and expert perspectives. Using this multi-method approach, researchers can attain a more comprehensive understanding of the impacts associated with BIM within the construction industry.

From design to construction to operations and maintenance, BIM impacts multiple phases of a project, and it can benefit a variety of stakeholders, including owners, designers, contractors and facility managers. Organizations can make informed decisions about whether to invest in BIM technology by quantifying its value for each of the phases and stakeholders and identify areas where BIM technology can be improved. Additionally, if organizations can quantify the value of BIM for the entire project life cycle and all stakeholders, they will be able to communicate the benefits of BIM more effectively to their clients, partners and other stakeholders, leading to increased adoption and increased project success. Figure 4 shows that 29% of the articles were not specific to a certain phase, rather the focus of those articles was to examine the ROI, the cost of the investment or a CBA generally.

Most of the research focused on the design stage, examined the effects of design optimization, reducing design errors, clash detections during the design stage and coordination between project stakeholders. Overall, 24% of the articles were focusing on design and construction integration, such as quantifying change orders costs, and the effect of BIM on enhancing opportunities for pre-fabrication and offsite construction. The effects of BIM on the post-construction phase had also received the attention of 12% of the analysed articles, in which the investment value was examined for operators and facility managers, in addition to a significant number of studies focusing on sustainability matters and optimizing energy consumption during the building operation:

RQ2.

What are the quantifiable factors that can be used to evaluate the investment value of BIM?

To answer the research question regarding the quantifiable factors that can be used to evaluate the investment value of BIM from the literature, an in-depth analysis had been conducted to extract all factors that were quantified in the examined articles. The articles in which an integrated method was used such as ROI and CBA were also examined to extract the factors that were considered to implement these quantification methods.

5.1 Quantification of building information modelling investment value using return on investment method

Several studies emphasized the importance of calculating BIM ROI to ensure that the construction organization understands the value of BIM. According to Sompolgrunk et al. (2022), ROI is a key principle for capturing the value of BIM. In addition to raising awareness of BIM ROI, the study is unique in providing a quantitative model which establishes the links and impact of various factors related to BIM ROI (Sompolgrunk et al., 2022). The investment value of BIM has been recently assessed internally by construction firms by developing their own BIM ROI quantification method (Lee and Lee, 2020), However, a lack of data, complexity of analysis, an extended time frame, intangible benefits, difficulty measuring productivity improvements and an inability to apply economic principles make this difficult (Ardani et al., 2022; Sompolgrunk et al., 2022).

There is currently no defined methodology for calculating BIM ROI in the industry. Based on the review of articles that address BIM ROI, it is evident that every project has its own unique characteristics, a number of stakeholders involved and other factors that could influence a ’project’s BIM ROI (Sompolgrunk et al., 2022; Sompolgrunk et al., 2023), and this is evident in the wide range of calculated ROI values from the literature. Figure 5 lists the identified ROI values in the analysed articles, and it can be stressed that the percentages vary significantly. However, all studies have reported a positive ROI value which emphasizes the fact that BIM will have a positive financial return on the project life cycle.

5.2 Quantification of building information modelling investment value using cost–benefit analysis

Another method used in the literature to evaluate ’BIM’s monetary impact is the CBA (Tu et al., 2023). The ROI measures the financial gain or loss relative to the investment cost and is solely focused on the financial return (Barlish and Sullivan, 2012). The CBA, however, considers both the financial and non-financial benefits of an investment, such as enhanced safety (Ardani et al., 2022). CBA provides a more comprehensive analysis of both financial and non-financial implications of BIM adoption, whereas ROI measures financial benefits such as reduced construction costs and improved productivity (Biancardo et al., 2023; Love et al., 2013).

As part of the CBA, all costs and benefits associated with BIM are identified and quantified, including those that are hard to quantify financially, such as improved safety, reduced rework and enhanced collaboration (Love et al., 2013; Zakeri et al., 2023). After comparing the benefits and costs, it is determined whether the investment is economically feasible (Sánchez et al., 2022). A number of benefits have been found to result from the use of BIM in the analysed literature, including improved productivity (Poirier et al., 2015), reduced construction costs (Yu et al., 2022) and enhanced collaboration, all of which can contribute to a higher ROI (Chen et al., 2022). The CBA involves calculating costs associated with the implementation of BIM, such as the cost of hardware and software, training and maintenance (Tu et al., 2023). The result of the CBA is usually reported as a final value of the difference between the summation of costs deducted from the summation of benefits, such as the results of the study by Khanzode et al. (2008), which applied CBA to examine the value of BIM for a health-care project. The results reported $9m in savings for the overall project (Khanzode et al., 2008). Another study by Kim et al. (2017) revealed that BIM has contributed to identifying and/or resolving issues whose contractual values are as much as 15.92% of the total direct cost of the project (Kim et al., 2017). Nevertheless, the analysis showed that few studies applied the CBA and presented numerical results. The majority of the articles examined the CBA concept from a theoretical lens with qualitative results (Biancardo et al., 2023; Hussain et al., 2023; Zhang et al., 2022).

5.3 Key attributes that were used in the literature to quantify financial impact of building information modelling

Several studies have tried to capture the value of BIM by focusing on one attribute solely and converting the impact of this attribute into cost. The main attributes that were studied in conjunction to BIM benefits quantification in the analysed literature varied according to the projects phase as shown earlier in Figure 4.

5.4 Productivity and processes

The productivity aspect has been discussed in the literature from two perspectives. The first view is that BIM increases construction project productivity in both the design and construction phases (Love et al., 2013; Poirier et al., 2015), and the second view is that the initial stages of implementing BIM will result in a reduction in productivity as a result of training, changing processes and adjusting to the new system (Sacks and Barak, 2008; Succar et al., 2012). Using BIM, project stakeholders can better communicate and collaborate, reduce rework costs and delays and get accurate and detailed information that streamlines construction processes and reduces project completion times.

The use of BIM has been shown to increase productivity and financial impact, according to some articles. As a result of reducing inefficiencies, improving communication and providing accurate and detailed information, BIM reduced labour work by 50% in a fast-track project (Abdelbary et al., 2020). Another study claimed that productivity increased by 27% in the case of small commercial franchising projects (Conde et al., 2020). The increase in productivity was also associated with BIM increasing the possibilities for pre-fabrication and off-site construction (Cucuzza et al., 2022). McGraw-Hill concluded that BIM enhanced pre-fabrication opportunities by 22%, which resulted in higher overall project productivity (McGraw-Hill, 2012). Also, Poirier et al. (2015) found that modelled and pre-fabricated areas had an increase in productivity of between 75% and 240% over areas that were not modelled (Poirier et al., 2015).

5.5 Changes, rework and design errors

Rework and design errors have always been regarded as major contributors to time and cost overruns in the construction industry. According to Abdelbary et al. (2020), rework increased project costs by 22% on average, resulting in a delay of 33 weeks on projects with an average planned duration of 156 weeks, a 23% delay from the original project value (Abdelbary et al., 2020).

It has been reported that BIM reduces rework, minimizes changes and prevents design errors by allowing designers to identify and resolve potential conflicts and issues before construction begins, as well as detect clashes in the design before they occur (Ham et al., 2018; Honnappa and Padala, 2022; Won et al., 2016). As a result of BIM, communication and collaboration are enhanced, resulting in faster decision-making, fewer errors and streamlined construction. This attribute has been quantified in the literature by converting the positive impact of reducing changes and errors into cost savings, improved project timelines and higher-quality outcomes. Abdelbary et al. (2020) also examined how BIM reduces rework in fast-track projects, with a savings of 10% ($10m) due to prevention of change orders, generated by clash detection in BIM (Abdelbary et al., 2020). An economic analysis of design errors in BIM-based high-rise projects (Ham et al., 2018) quantified a reduction in rework by 5%–20%, resulting in 47% savings.

5.6 Requests for information

A typical construction project will involve numerous requests for information (RFIs) that can be time-consuming and expensive (Morales et al., 2022). However, with the use of BIM, the number of RFIs can be greatly reduced (Toan et al., 2022; Zakeri et al., 2023). To prevent errors and omissions that would typically result in RFIs during construction, BIM allows construction professionals to collaborate and identify potential issues before construction begins (Tu et al., 2023). BIM can also reduce the time required to respond to RFIs by providing a centralized platform for information sharing. Abdelbary et al. (2020) analysed several case studies and found that the use of BIM had reduced the number of RFIs by 90%. With all project data available in one place, the project team can respond to RFIs quickly and accurately, reducing time and costs (Morales et al., 2022). Furthermore, BIM can make it easier to track RFIs and ensure timely resolution, which can help prevent delays and keep projects on schedule. A study by Barlish and Sullivan (2012) evaluated the time saved by reducing RFIs through BIM, and they noticed a reduction in the number of RFIs by 30%, with an evaluation of 5% cost savings and 67% less time delays (Barlish and Sullivan, 2012).

5.7 Schedule reduction

Overall, studies have consistently shown that the use of BIM can significantly improve productivity and save time and costs in the construction industry, making it a valuable tool for construction projects, in which time overruns have always been jeopardizing projects’ performance. A report by McGraw-Hill Construction found that BIM can lead to a reduction in project costs and schedules by up to 50%, with the use of BIM leading to improved project coordination, fewer errors and omissions and a reduction in RFIs (McGraw-Hill, 2012). Another research proposed a BIM framework to quantify delays and cost overruns that are attributed to changes and found that BIM contributed to 11% of the time savings (Honnappa and Padala, 2022).

5.8 Safety and environment

There has also been significant literature regarding BIM’s association with sustainability. First, it provides accurate and detailed information about building systems, such as HVAC, lighting and energy usage, which can help optimize building performance (Choi and Lee, 2023). Building designers can use this information to make more informed decisions regarding building design, energy efficiency and resource usage, resulting in sustainable and environmentally friendly buildings (Choi and Lee, 2023; Li et al., 2023). Ferreira et al. (2023) examined the impact of design optimization using BIM and concluded that enhanced energy consumption can result in a 2%–5% total savings (Ferreira et al., 2023). A similar study examined the optimization of design to achieve sustainability, in which BIM reduced water consumption in the building by up to 60% (Hasanain and Nawari, 2022).

Secondly, BIM can help reduce waste and increase efficiency in the construction process by allowing project teams to identify and resolve potential issues before construction begins (Hasanain and Nawari, 2022). This can help reduce the amount of material waste, energy usage and environmental impact associated with the construction process. Banihashemi et al. (2018) proposed a construction waste reduction workflow and demonstrated how BIM can save around 2% of additional waste (Banihashemi et al., 2018). Similarly, a BIM-based design validation prevented 4.3%–15.2% of construction waste on sites according to Won et al. (2016).

5.9 Operations and facility management

BIM for operations and facility management applies BIM technology to effectively manage building facilities throughout their life cycle (Yu et al., 2022). It optimizes asset management, space utilization, energy efficiency and sustainability while streamlining documentation and supporting emergency planning (Blampain et al., 2023; Lu et al., 2023). Facility management that integrates BIM reduces costs, improves performance and improves occupant satisfaction (Toan et al., 2022). Sixty percent of respondents to a survey by PWC reported achieving cost savings in their asset management operations through BIM (PWC, 2018). Conde et al. (2020) proposed a simplified method for BIM implementation in operations and maintenance and concluded that significant time savings could be achieved through BIM for the facility management phase (Conde et al., 2020):

RQ3.

What are the current research gaps in BIM investment evaluation state of the art?

An analysis of previous research trends regarding BIM investment value is provided in this systematic review. Based on the analysis, gaps in the body of knowledge regarding BIM investment value and feasibility were identified. These gaps are as follows:

  • There is a lack of an industry-established method for quantifying and benchmarking the BIM investment value.

  • ’BIM’s intangible benefits for construction projects are not sufficiently addressed.

Despite numerous studies examining the impact of BIM on productivity, cost savings and related metrics, there remains a lack of standardized methods for calculating its economic implications. This absence of a standardized approach poses challenges for construction professionals, particularly when justifying the associated costs of implementing BIM technologies—a significant investment in itself. Presently, many in the construction industry rely on case studies and project-specific data to evaluate the feasibility of BIM investments. However, these efforts remain fragmented, tailored to individual organizational processes and methodologies, making cross-industry result comparisons and benchmarking a complex task.

To address this issue and facilitate the quantification and benchmarking of BIM investment value, it is imperative to develop a standardized method. Such a method would not only aid construction professionals in making informed decisions regarding BIM technology adoption but also enable them to accurately assess the costs and benefits associated with its implementation.

Moreover, the application of standardized methods can serve to substantiate BIM investments when presenting proposals to stakeholders such as owners, investors and clients. Demonstrating the economic returns through standardized metrics can bolster the case for securing funding and garnering support for these initiatives.

Furthermore, the establishment of a standardized approach for quantifying BIM investments can foster innovation and advancement within the construction sector. Through the adoption of industry-wide standards for BIM implementation and investment value assessment, construction professionals can collaborate to identify and implement best practices, leading to enhanced utilization of these technologies and, ultimately, improved project outcomes. Therefore, the importance of a standardized method for quantifying and benchmarking BIM investments cannot be overstated, as it contributes to informed decision-making, funding acquisition, and industry progress.

Additionally, there exists a research gap that overlooks the financial evaluation of intangible benefits stemming from BIM implementation in construction projects, despite the potential for these benefits to yield superior project outcomes, heightened efficiency and enhanced long-term sustainability. In essence, BIM possesses the capacity to enhance project outcomes, boost efficiency and elevate long-term sustainability primarily through its intangible advantages. Construction professionals can attain a comprehensive understanding and recognition of the enduring value that BIM brings to their projects by duly acknowledging and addressing these intangible benefits.

BIM in construction projects may have intangible benefits that are difficult to quantify, but over time, they can have significant economic value. It is important to collaborate and communicate effectively in order to improve project outcomes and make better decisions, which can increase client satisfaction and lead to repeat business. A construction company can significantly increase revenue and profits by implementing this strategy. Visualizing and understanding project designs can reduce the likelihood of costly errors or rework, improving project timelines, reducing costs and improving quality. The resulting reduction in expenses and increase in efficiency can also have a significant impact on the bottom line of a construction company.

Similarly, improving efficiency and accuracy in project planning and execution can lead to long-term savings, increased productivity, and improved project outcomes by reducing the likelihood of costly mistakes or delays. Construction companies can benefit from this by increasing profits and improving their competitive position in the market. In addition, ’BIM’s ability to provide accurate and detailed information can contribute to long-term economic benefits by reducing waste and minimizing the environmental impact of construction projects. Over time, this could lead to lower operating costs and greater value for buildings and infrastructure. Thus, by excluding the intangible factors and their economic value from the BIM investment value calculation, the construction industry is losing the opportunity to accurately measure ’BIM’s economic impact.

6. Conclusion

In conclusion, this research has unearthed pivotal insights into the quantification of BIM benefits. Key findings include the identification of ROI calculation as the primary method for assessing ’BIM’s tangible benefits. Two significant research gaps are highlighted: the absence of a standardized BIM ROI method and the limited exploration of intangible benefits. Quantifiable factors for BIM investment value assessment are categorized, encompassing productivity, changes and rework reduction, RFIs reduction, schedule efficiency, safety, environmental sustainability and operations and facility management. These specific findings provide actionable insights for researchers and practitioners, offering a clear road map for further exploration and development in the construction industry.

This research presents tangible contributions to the field of BIM. The identification of ROI as the primary quantification method and the spotlight on research gaps offer practical guidance for industry professionals. By addressing the absence of a standardized BIM ROI method, this research lays the foundation for streamlined decision-making in BIM technology adoption. The exploration of intangible benefits underscores the potential for enhanced project outcomes, efficiency and long-term sustainability. Categorizing quantifiable factors provides a road map for optimizing BIM implementation, leading to increased productivity, reduced costs, improved safety and environmentally conscious construction practices. These findings not only empower researchers and practitioners but also contribute to the industry's evolution towards more informed, sustainable and efficient construction practices.

In conclusion, the study recommends that future research be directed towards establishing a common method for measuring BIM investment value for industry use based on the identified gaps. As a result of such tool, the construction industry will become more aware of the feasibility of BIM, which will lead to more sustainable, productive and efficient benefits.

Figures

Flow diagram of research methodology

Figure 1.

Flow diagram of research methodology

Distribution of selected articles per year

Figure 2.

Distribution of selected articles per year

Research methods used in the analysed literature

Figure 3.

Research methods used in the analysed literature

Distribution of the articles focus per project phase

Figure 4.

Distribution of the articles focus per project phase

Quantified values of BIM benefits from the literature

Figure 5.

Quantified values of BIM benefits from the literature

Keywords search

Round Keywords
1 BIM, Rate of return, cost, investment
2 BIM, benefits, time, cost, sustainability
3 BIM, life cycle, implementation
4 BIM, rework, design, construction, waste

Source: Authors’ own creation

Literature sources classification

Journal articles 72%
Automation in Construction 8
Sustainability 5
Journal of Construction Engineering and Management 4
Journal of Civil Engineering and Management 3
Buildings 2
Energies 2
Energy And Buildings 2
Journal of Building Engineering 2
Journal of Information Technology in Construction 2
Waste Management 2
Other 22
Conference articles 18%
Industry reports and research 10%
McGraw-Hill Construction 2
PWC 1
Other 4
Total 75

Source: Authors’ own creation

References

Abdelbary, M., Edkins, A. and Dorra, E. (2020), “Reducing CRR in fast-track projects through BIM”, Journal of Information Technology in Construction, Vol. 25, pp. 140-160, doi: 10.36680/j.itcon.2020.009.

Ardani, J.A., Utomo, C., Rahmawati, Y. and Nurcahyo, C.B. (2022), “Review of previous research methods in evaluating BIM investments in the AEC industry”, Proceedings of the 5th International Conference on Sustainable Civil Engineering Structures and Construction Materials, Singapore.

Azhar, S. (2011), “Building information modeling (BIM): trends, benefits, risks, and challenges for the AEC industry”, Leadership and Management in Engineering, Vol. 11 No. 3, pp. 241-252, doi: 10.1061/(ASCE)LM.1943-5630.0000127.

Banihashemi, S., Tabadkani, A. and Hosseini, M.R. (2018), “Integration of parametric design into modular coordination: a construction waste reduction workflow”, Automation in Construction, Vol. 88, pp. 1-12, doi: 10.1016/j.autcon.2017.12.026.

Barlish, K. and Sullivan, K. (2012), “How to measure the benefits of BIM - A case study approach [article]”, Automation in Construction, Vol. 24, pp. 149-159, doi: 10.1016/j.autcon.2012.02.008.

Biancardo, S.A., Gesualdi, M., Savastano, D., Intignano, M., Henke, I. and Pagliara, F. (2023), “An innovative framework for integrating cost-benefit analysis (CBA) within building information modeling (BIM) [article]”, Socio-Economic Planning Sciences, Vol. 85, p. 101495, doi: 10.1016/j.seps.2022.101495.

Blampain, F., Bricogne, M., Eynard, B., Bricogne, C. and Pinon, S. (2023), “Digital thread and building lifecycle management for industrialisation of construction operations: a state-of-the-Art review”, Lecture Notes in Mechanical Engineering, pp. 884-894.

Chen, X., Qi, W. and Hu, W. (2022), “Cost-Effective analysis and calculation of energy performance using insight tool in BIM”, 2022 IEEE 2nd International Conference on Electronic Technology, Communication and Information, ICETCI 2022.

Choi, J. and Lee, S. (2023), “A suggestion of the alternatives evaluation method through IFC-based building energy performance analysis [article]”, Sustainability,), Vol. 15 No. 3, p. 1797, doi: 10.3390/su15031797.

Conde, A.J., Sanz-Calcedo, J. and Reyes-Rodríguez, A. (2020), “Use of BIM with photogrammetry support in small construction projects. Case study for commercial franchises”, Journal of Civil Engineering and Management, Vol. 26, pp. 513-523, doi: 10.3846/jcem.2020.12611.

Condotta, M. and Scanagatta, C. (2023), “BIM-based method to inform operation and maintenance phases through a simplified procedure [article]”, Journal of Building Engineering, Vol. 65, p. 105730, doi: 10.1016/j.jobe.2022.105730.

Cucuzza, M., Di Stefano, A.G., Iannaccone, G. and Masera, G. (2022), “A BIM-enabled decision support system to support large-scale energy retrofitting processes and off-site solutions for envelope insulation”, IOP Conference Series: Earth and Environmental Science, Vol. 1101 No. 4.

Daszczyński, T., Ostapowski, M. and Szerner, A. (2022), “Clash cost analysis in electrical installations based on BIM technologies [article]”, Energies, Vol. 15 No. 5, p. 1679, doi: 10.3390/en15051679.

Feng, H., Kassem, M., Greenwood, D. and Doukari, O. (2023), “Whole building life cycle assessment at the design stage: a BIM-based framework using environmental product declaration [article]”, International Journal of Building Pathology and Adaptation, Vol. 41 No. 1, pp. 109-142, doi: 10.1108/IJBPA-06-2021-0091.

Ferreira, A., Pinheiro, M.D., Brito, J.D., Mateus, R. and Mendonça, R. (2023), “Wall and roof solutions for a retail building considering cost investment and life cycle approach: a case study in Portugal [article]”, Journal of Cleaner Production, Vol. 383, p. 135314, doi: 10.1016/j.jclepro.2022.135314.

Gharaibeh, L., Matarneh, S.T., Eriksson, K. and Lantz, B. (2022), “An empirical analysis of barriers to building information modelling (BIM) implementation in wood construction projects: evidence from the Swedish context”, Buildings, Vol. 12 No. 8, p. 1067, available at: www.mdpi.com/2075-5309/12/8/1067

Ham, N., Moon, S., Kim, J.H. and Kim, J.-J. (2018), “Economic analysis of design errors in BIM-based high-rise construction projects: Case study of Haeundae L project”, Journal of Construction Engineering and Management, Vol. 144 No. 6, p. 5018006, doi: 10.1061/(ASCE)CO.1943-7862.0001498.

Harris, M., Ismail, E. and Hussain, A.H. (2015), “Business value of BIM in Malaysia's AEC industry: preliminary findings [article]”, Malaysian Construction Research Journal, Vol. 16 No. 1, pp. 31-41, available at: www.scopus.com/inward/record.uri?eid=2-s2.0-84976321968&partnerID=40&md5=874fa3068534d1a926442c841912a5fe

Hasanain, F.A. and Nawari, N.O. (2022), “BIM-based model for sustainable built environment in Saudi Arabia [article]”, Frontiers in Built Environment, Vol. 8, p. 950484, doi: 10.3389/fbuil.2022.950484.

Honnappa, D. and Padala, S.P.S. (2022), “BIM-based framework to quantify delays and cost overruns due to changes in construction projects [article]”, Asian Journal of Civil Engineering, Vol. 23 No. 5, pp. 707-725, doi: 10.1007/s42107-022-00451-x.

Hosseini, M.R., Banihashemi, S., Chileshe, N., Oraee, M., Udeaja, C., Rameezdeen, R. and McCuen, T. (2016), “BIM adoption within Australian small and medium-sized enterprises (SMEs): an innovation diffusion model”, Construction Economics and Building, Vol. 16 No. 3, pp. 71-86, doi: 10.5130/AJCEB.v16i3.5159.

Hussain, M., Zheng, B., Chi, H.L. and Hsu, S.C. (2023), “Automated and continuous BIM-based life cycle carbon assessment for infrastructure design projects [article]”, Resources, Conservation and Recycling, Vol. 190, p. 106848, doi: 10.1016/j.resconrec.2022.106848.

Hwang, B.-G. and Zhao, X. (2018), “The effect of BIM on rework in construction projects in Singapore: status quo, magnitude, impact and strategies”, Journal of Construction Engineering and Management, doi: 10.1061/(ASCE)CO.1943-7862.0001600.

Khanzode, A., Fischer, M. and Reed, D. (2008), “Benefits and lessons learned of implementing building virtual design and construction (VDC) technologies for coordination of mechanical, electrical, and plumbing (MEP) systems on a large healthcare project”, Journal of Information Technology in Construction (ITcon), Vol. 13 No. 22, pp. 324-342.

Kim, H., Kim, S.-K. and Kang, L.-S. (2020), “BIM performance assessment system using a K-means clustering algorithm”, Journal of Asian Architecture and Building Engineering, Vol. 20 No. 1, pp. 1-10, doi: 10.1080/13467581.2020.1800471.

Kim, Y.O., Lee, D.H. and Park, D.H. (2022), “A case study on BIM Object-Based earned value and process management in highway construction [article]”, KSCE Journal of Civil Engineering, Vol. 26 No. 2, pp. 522-538, doi: 10.1007/s12205-021-1348-3.

Kim, S., Chin, S., Han, J. and Choi, C.-H. (2017), “Measurement of construction BIM value based on a case study of a large-scale building project”, Journal of Management in Engineering, Vol. 33 No. 6, doi: 10.1061/(ASCE)ME.1943-5479.0000551.

Kineber, A.F., Massoud, M.M., Hamed, M.M., Alhammadi, Y. and Al-Mhdawi, M.K.S. (2023), “Impact of overcoming BIM implementation barriers on sustainable building project success: a PLS-SEM approach [article]”, Buildings, Vol. 13 No. 1, p. 178, doi: 10.3390/buildings13010178.

Kitchenham, B. (2004), Procedures for Performing Systematic Reviews, Keele University, Keele, UK, Vol. 33 No. 2004, pp. 1-26.

Krystallis, I., Papadonikolaki, E., Locatelli, G. and Iuorio, O. (2019), “Towards a methodology for quantifying the benefits of BIM”, Proceedings of the 2019 European Conference on Computing in Construction, Crete.

Latiffi, A.A. and Tai, N.H. (2017), “Exploring developers' understanding on building information modelling (BIM) and its impact on return on investment (ROI)”, International Conference on Research and Innovation in Information Systems, ICRIIS.

Lee, M. and Lee, U.-K. (2020), “A framework FOR evaluating AN integrated BIM ROI based ON preventing rework IN THE construction phase”, Journal OF Civil Engineering AND Management, Vol. 26 No. 5, pp. 410-420, doi: 10.3846/jcem.2020.12185.

Lee, M., Cha, M.-S. and Lee, U.-K. (2018), “Analysis of BIM impact on preventing rework in construction phase”, Journal of the Korea Institute of Building Construction, Vol. 18, pp. 169-176, doi: 10.5345/JKIBC.2018.18.2.169.

Li, Q., Yang, W., Kohler, N., Yang, L., Li, J., Sun, Z., Yu, H., Liu, L. and Ren, J. (2023), “A BIM–LCA approach for the whole design process of green buildings in the Chinese context [article]”, Sustainability, Vol. 15 No. 4, p. 3629, doi: 10.3390/su15043629.

Love, P.E.D., Simpson, I., Hill, A. and Standing, C. (2013), “From justification to evaluation: building information modeling for asset owners”, Automation in Construction, Vol. 35, pp. 208-216, doi: 10.1016/j.autcon.2013.05.008.

Lu, K., Deng, X., Jiang, X., Cheng, B. and Tam, V.W.Y. (2023), “A review on life cycle cost analysis of buildings based on building information modeling [article]”, Journal OF Civil Engineering AND Management, Vol. 29 No. 3, pp. 268-288, doi: 10.3846/jcem.2023.18473.

McGraw-Hill (2012), “The business value of BIM in North America: multi-year trend analysis and user ratings”.

Morales, F., Herrera, R.F., Rivera, F.M.L., Atencio, E. and Nuñez, M. (2022), “Potential application of BIM in RFI in building projects [article]”, Buildings, Vol. 12 No. 2, p. 145, doi: 10.3390/buildings12020145.

Motalebi, M., Rashidi, A. and Nasiri, M.M. (2022), “Optimization and BIM-based lifecycle assessment integration for energy efficiency retrofit of buildings [article]”, Journal of Building Engineering, Vol. 49, p. 104022, doi: 10.1016/j.jobe.2022.104022.

Nightingale, A. (2009), “A guide to systematic literature reviews”, Surgery (Oxford), Vol. 27 No. 9, pp. 381-384, doi: 10.1016/j.mpsur.2009.07.005.

Okoli, C. (2015), “A guide to conducting a standalone systematic literature review”, Communications of the Association for Information Systems, 37, available at: https://hal.science/hal-01574600

Poirier, E., Staub-French, S. and Forgues, D. (2015), “Measuring the impact of BIM on labor productivity in a small specialty contracting enterprise through action-research”, Automation in Construction, Vol. 58, pp. 74-84, doi: 10.1016/j.autcon.2015.07.002.

Primasetra, A., Larasati, D. and Wonorahardjo, S. (2022), “BIM utilization in improving energy efficiency performance on architectural design process: challenges and opportunities”, IOP Conference Series: Earth and Environmental Science, Vol. 1058 No. 1.

PWC (2018), “BIM level 2 benefits measurement application of PwC’s BIM level 2 benefits measurement methodology to public sector capital assets”.

Qian, A.Y. (2012), “Benefits and ROI of BIM for multi-disciplinary project management”.

Sabbaghzadeh, M., Sheikhkhoshkar, M., Talebi, S., Rezazadeh, M., Rastegar Moghaddam, M. and Khanzadi, M. (2022), “A BIM-Based solution for the optimisation of fire safety measures in the building design”, Sustainability, Vol. 14 No. 3, p. 1626. available at: https://www.mdpi.com/2071-1050/14/3/1626

Sacks, R. and Barak, R. (2008), “Impact of three-dimensional parametric modeling of buildings on productivity in structural engineering practice”, Automation in Construction, Vol. 17 No. 4, pp. 439-449, doi: 10.1016/j.autcon.2007.08.003.

Sánchez, O., Castañeda, K., Herrera, R.F. and Pellicer, E. (2022), “Benefits of building information modeling in road projects for cost overrun factors mitigation”, Construction Research Congress 2022: Project Management and Delivery, Controls, and Design and Materials – Selected Papers from Construction Research Congress 2022.

Sheikhkhoshkar, M., Khanzadi, M. and Banihashemi, S. (2018), “BIM applications toward key performance indicators of construction projects in Iran”, International Journal of Construction Management, Vol. 20 No. 4, doi: 10.1080/15623599.2018.1484852.

Sompolgrunk, A., Banihashemi, S., Hosseini, M.R., Golzad, H. and Hajirasouli, A. (2022), “An integrated model of BIM return on investment for Australian small- and medium-sized enterprises (SMEs) [article]”, Engineering, Construction and Architectural Management, doi: 10.1108/ECAM-09-2021-0839.

Sompolgrunk, A., Banihashemi, S. and Mohandes, S.R. (2023), “Building information modelling (BIM) and the return on investment: a systematic analysis [review]”, Construction Innovation, Vol. 23 No. 1, pp. 129-154, doi: 10.1108/CI-06-2021-0119.

Succar, B., Sher, W. and Williams, A. (2012), “Measuring BIM performance: five metrics”, Architectural Engineering and Design Management, Vol. 8 No. 2, pp. 120-142, doi: 10.1080/17452007.2012.659506.

Toan, N.Q., Van Tam, N., Diep, T.N. and Anh, P.X. (2022), “Adoption of building information modeling in the construction project life cycle: benefits for stakeholders [article]”, Architecture and Engineering, Vol. 7 No. 1, pp. 56-71, doi: 10.23968/2500-0055-2022-7-1-56-71.

Tu, B., Pan, M., Zuo, J., Chang, R.D., Webber, R.J., Zou, Z. and Dong, N. (2023), “Cost–benefit analysis of construction waste source reduction: a system dynamics approach [article]”, Environmental Science and Pollution Research, Vol. 30 No. 1, pp. 557-577, doi: 10.1007/s11356-022-22148-z.

Won, J., Cheng, J.C.P. and Lee, G. (2016), “Quantification of construction waste prevented by BIM-based design validation: Case studies in South Korea”, Waste Management, Vol. 49, pp. 170-180, doi: 10.1016/j.wasman.2015.12.026.

Xenidis, Y. and Koukoulis, A. (2022), “Earned value management with the use of building information modelling”, International Conference on Construction in the 21st Century.

Yu, J., Wang, J., Hua, Z. and Wang, X. (2022), “BIM-based time-cost optimization of a large-span spatial steel structure in an airport terminal building [article]”, Journal of Facilities Management, Vol. 20 No. 3, pp. 469-484, doi: 10.1108/JFM-12-2020-0097.

Zakeri, S.M.H., Tabatabaee, S., Ismail, S., Mahdiyar, A. and Wahab, M.H. (2023), “Developing an MCDM model for the benefits, opportunities, costs and risks of BIM adoption [article]”, Sustainability,), Vol. 15 No. 5, p. 4035, doi: 10.3390/su15054035.

Zhang, Y., Jiang, X., Cui, C. and Skitmore, M. (2022), “BIM-based approach for the integrated assessment of life cycle carbon emission intensity and life cycle costs [article]”, Building and Environment, Vol. 226, p. 109691, doi: 10.1016/j.buildenv.2022.109691.

Zhao, L., Zhang, W. and Wang, W. (2022), “BIM-based multi-objective optimization of low-carbon and energy-saving buildings [article]”, Sustainability,), Vol. 14 No. 20, p. 13064, doi: 10.3390/su142013064.

Further reading

Bimalliance (2023), “BIM alliance Sweden”, [accessed Jan 2023].

Corresponding author

Lina Gharaibeh can be contacted at: lina.gharaibeh@hv.se

About the authors

Lina Gharaibeh, Researcher in production technology focusing on supply chain and logistics, is from a construction management background, with a Bachelor of Civil Engineering and almost 12 years of experience in the construction sector. Skilled in project planning, construction management, project management, logistics and project delivery, as well as has a Master of Science – MSc focused on Construction Management. Since joining University West in March 2020 as a PhD student, Lina Gharaibeh has been investigating the digitalization and optimization of supply chain and logistics using BIM and Industry 4.0 technologies.

Kristina Eriksson, Associate Professor in production systems, at University West, focusses on teaching and research in production logistics, supply chain management and simulation of production flows. Kristina Eriksson has substantial experience and educational and research interest in industrial work integrated learning, specifically flexible e-learning concepts for competence development in collaboration with industrial companies.

Björn Lantz, Professor in operations management at Chalmers and Visiting Professor in Logistics at University West, has worked in a number of different research areas over the years, for example, e-commerce, supply chain risk management, diffusion of innovations, queuing theory and quantitative research methodology. Their primary research area is healthcare production logistics where the focus is on different aspects of capacity management.

Related articles