Genetic Algorithms Multi-Objective Model for Project Scheduling

Creators

Description

Time and cost are the main goals of the construction
project management. The first schedule developed may not be a
suitable schedule for beginning or completing the project to achieve
the target completion time at a minimum total cost. In general, there
are trade-offs between time and cost (TCT) to complete the activities
of a project. This research presents genetic algorithms (GAs) multiobjective
model for project scheduling considering different
scenarios such as least cost, least time, and target time.

Files

9999947.pdf

Files (79.7 kB)

Name Size Download all
md5:2bbccba8c7be04bdc11e896573c1d42e
79.7 kB Preview Download

Additional details

References

  • Liu, L., Burns, S., and Feng, C., "Construction Time-Cost Trade-Off Analysis Using LP/IP Hybrid Method," Journal of Construction Engineering and Management, ASCE, 121(4), 446-454, 1995.
  • Maghrebi, M., Afshar, A., and Maghrebi, M. J., "A Novel Mathematical Model for Deterministic Time-cost Trade-off Based on Path Constraint," International Journal of Construction Engineering and Management 2(5): 137-142, 2013.
  • Zheng, D., Ng, S. T., and Kumaraswamy, M., "Applying a Genetic Algorithm-Based Multiobjective Approach for Time-Cost Optimization," Journal of Construction Engineering and Management, ASCE, 130(2), 168-176, 2004.
  • Forrest, S., "Genetic Algorithms: Principles of Natural Selection Applied to Computation", Science 261, 1993.
  • Feng, C., Liu, L., and Burns, S., "Using genetic algorithms to solve construction time–cost trade-off problems," ASCE Journal of Computing in Civil Engineering, 11(3), 184–189, 1997.
  • Li, H., Cao, J.-N., and Love, P., "Using Machine Learning and GA to Solve Time-Cost Trade-Off Problems," Journal of Construction Engineering and Management, ASCE, 125(5), 347-353, 1999.
  • Hegazy, T., "Optimization of construction time–cost trade-off analysis using genetic algorithms," Canadian Journal of Civil Engineer Vol. 26, 685–697, 1999.
  • Ammar, M. A., "Optimization of project time-cost trade-off problem with discounted cash flows," Journal of Construction Engineering and Management, 137(1), 65-71, 2010.
  • Aghassi, H., et al., "a multi-objective Genetic Algorithm for optimization time-cost trade-off scheduling," Knowledge Technology, Springer, 356-359, 2012. [10] Ghoddousi, P., et al., "Multi-mode resource-constrained discrete time– cost-resource optimization in project scheduling using non-dominated sorting genetic algorithm," Automation in Construction, 216–227, 2013. [11] Bettemir, Ö.H., "Experimental Design for Genetic Algorithm Simulated Annealing For Time Cost Trade-Off Problems," International Journal of Engineering & Applied Sciences (IJEAS) Vol.3, Issue 1, 15-26, 2011.