Analisis Jaringan Kerja dengan Metode Critical Path Method (CPM) dan Model Program Linier

Authors

  • Switamy Angnitha Purba Universitas HKBP Nommensen Pematangsiantar

DOI:

https://doi.org/10.30606/absis.v4i1.993

Keywords:

Network Analysis, Critical Path Method, Linear programming

Abstract

Network analysis is part of a project that requires time for each network activity. To produce a particular project there is more than one job/event that must be done. Each job/event is interconnected and placed in order according to the management of its implementation. In network projects, it is necessary to plan and supervise systematically, in order to obtain work efficiency. The network is represented in symbols and arrows. In this study, the problem-solving network analysis was solved using the CPM (Critical Path Method) method and with a linear programming model using the help of excel-solver and Lingo. This study aims to compare the two methods in solving network analysis problems. Based on the analysis, it is found that by using the CPM method, more critical paths are obtained than the linear programming method. With the increasing number of critical paths obtained, it is hoped that the management can determine project priorities to maintain the project schedule to be completed on time.

Downloads

Download data is not yet available.

References

Abrar, Husein. 2008. Manajemen Proyek, Perencanaan, Penjadwalan & Pengendalian Proyek. Yogyakarta: Andi Offset.

Asri, D. F., Setiawan, T. H., & Rusdiana, Y. 2020. Analisis Jaringan Kerja pada Evaluasi Pencadwalan Waktu dam Biaya Penyelesaian Proyek dengan Menggunakan Metode PERT & CPM. Jurnal Saintika UNPAM Vol. 2. No. 2.

Ayu, N. 2010. Perancangan Perangkat Lunak Pembentukan Jalur Kritis dari Suatu Jaringan Kerja Proyek. Skripsi tidak diterbitkan. Medan: Universitas Sumatera Utara.

Badri, Sofwan. 1991. Dasar-dasar Network Planning. Jakarta: PT. Rineka Cipta.

Handayani, Elvira. 2014. Analisis Jaringan Kerja dan Penentuan Jalur Kritis dengan Critical Path Methode- CPM (Studi Kasus Pembangunan Pendopo Balai Adat Provinsi Jambi). Jurnal Ilmiah Universitas Batanghari Jambi Vol. 14 No. 2.

Maranresy, P., Sompie, B.F., & Pratasis, P. 2015. Sistem Pengendalian Waktu Pada Pekerjaan Konstruksi Jalan Raya dengan Menggunakan Metode CPM. Jurnal Sipil Statik. Vol 3(1), pp: 8-15.

Nalhadi, A., & Suntana, N. 2018. Analisa Infrastruktur Desa Sukaci-Baros Dengan Metode Critical Path Method (CPM). J. Sist. Dan Manaj. Ind., Vol. 1, No. 1.

Siagian, M.D., Siregar, R., & Nasution, E.A. 2019. Optimalisasi Penjadwalan dengan Analisis Jaringan Kerja pada Kegiatan Verifikasi Koleksi Buku di Perpustakaan Sekolah. InfoTekJar : Jurnal Nasional Informatika dan Teknologi Jaringan. Vol. 4, No. 1.

Soeharto, Iman. 1995. Manajemen Proyek dan Konseptual Sampai Operasional. Jakarta: Erlangga.

Sugiyarto, Qomariyah, S., & Hamzah, F. 2013. Analisis Network Planning Dengan Cpm (Critical Path Method) Dalam Rangka Efisiensi Waktu Dan Biaya Proyek. e-Jurnal Matriks Teknik Sipil, Vol. 1 No. 4.

Downloads

Published

2021-10-30

How to Cite

Purba, S. A. (2021). Analisis Jaringan Kerja dengan Metode Critical Path Method (CPM) dan Model Program Linier. Jurnal Absis: Jurnal Pendidikan Matematika Dan Matematika, 4(1), 429–438. https://doi.org/10.30606/absis.v4i1.993

Similar Articles

1 2 3 4 5 > >> 

You may also start an advanced similarity search for this article.