Status of the Utility System Construction for the 3 GeV TPS Storage Ring |
Authors |
- J.-C. Chang, W.S. Chan, C.S. Chen, J.-R. Chen, Y.-C. Chung, C.W. Hsu, K.C. Kuo, Y.-C. Lin, C.Y. Liu, Y.-H. Liupresenter, Z.-D. Tsai, T.-S. Ueng
NSRRC, Hsinchu, Taiwan
|
Abstract |
The construction of the utility system for the 3.0 GeV Taiwan Photon Source (TPS) was started in the end of 2009. The utility building for the TPS ring had been completed in the end of 2013. The building use license had been approved in Sep. 2013. The whole construction engineering has been completed. The acceptance test is scheduled on July 2014. Total budget of this construction is about four million dollars. This utility system presented in this paper includes the cooling water, air conditioning, electrical power, and compressed air systems.
|
Paper |
download THPME200.PDF [3.291 MB / 3 pages] |
Export |
download ※ BibTeX
※ LaTeX
※ Text/Word
※ RIS
※ EndNote |
Conference |
IPAC2014, Dresden, Germany |
Series |
International Particle Accelerator Conference (5th) |
Proceedings |
Link to full IPAC2014 Proccedings |
Session |
Poster Session, Messi Area |
Date |
19-Jun-14 16:00–18:00 |
Main Classification |
07 Accelerator Technology Main Systems |
Sub Classification |
T21 Infrastructures |
Keywords |
storage-ring, booster, controls, operation, power-supply |
Publisher |
JACoW Publishing, Geneva, Switzerland |
Editors |
Christine Petit-Jean-Genaz (CERN, Geneva, Switzerland); Gianluigi Arduini (CERN, Geneva, Switzerland); Peter Michel (HZDR, Dresden, Germany); Volker RW Schaa (GSI, Darmstadt, Germany) |
ISBN |
978-3-95450-132-8 |
Published |
July 2014 |
Copyright |
|