To read this content please select one of the options below:

Investigating the causes preventing the fulfillment of construction contract requirements

Fadi A. Fatayer (Department of Building Engineering, An-Najah National University, Nablus, Palestinian Authority)
Amjad Z. Issa (Department of Civil Engineering, An-Najah National University, Nablus, Palestinian Authority)
Mohammed Abunemeh (Department of Civil Engineering, An-Najah National University, Nablus, Palestinian Authority)
Mohammed A.M. Dwikat (Department of Management Information System, An-Najah National University, Nablus, Palestinian Authority)

Engineering, Construction and Architectural Management

ISSN: 0969-9988

Article publication date: 15 June 2021

Issue publication date: 3 August 2022

524

Abstract

Purpose

Construction contractors in Palestine, as in many other developing countries, suffer from many problems. One of their main problems is their inability to meet contractual requirements, such as completing projects within time, at the agreed cost and to the desired quality. Therefore, this paper aims to investigate the causes of the non-fulfillment of contractual requirements in three different types of projects: building, road and electro-mechanical projects.

Design/methodology/approach

Two methods were adopted to collect the data – qualitative and quantitative. In total, 65 causes were identified from the literature and qualitative semi-structured interviews with professional experts. These causes were classified into five categories: managerial, financial, contractor capabilities, regulations and laws and political. In the quantitative approach, a questionnaire was developed and then distributed to 50 professional experts: 20 building experts, 15 road experts and 15 experts in electro-mechanical projects. A five-point Likert scale was used to assess the importance, from the perspective of the subject matter experts, of the causes that had been identified. About 35 responses, which represent a combined response rate of 70%, were received. The quantitative data were analyzed using descriptive statistics, with the mean, standard deviation and degree of importance for each of the identified causes being determined, and the SPSS software platform used to rank them.

Findings

The results reveal that the most important reasons why contractors did not fulfill their contractual requirements in building projects were that contracts were awarded to the contractor offering the lowest price, and the profit margin was low because of intense competition among contractors. In road projects, the most important causes were the poor estimation of the equipment required and a lack of standardized conditions in the construction sector, while in electro-mechanical projects, the most important causes were the inability of the contractor to estimate the cost of the project accurately because of unclear bid documents and a lack of contractor capital.

Originality/value

The results of this study will be useful to stakeholders and Palestinian contractor unions. They can be disseminated to give guidance so that contractors can avoid these problems in future construction projects and enhance their compliance with contractual requirements. Moreover, knowing about these causes may lead to the reduction of conflicts and disputes between contractual parties (owners and contractors), which in turn will be reflected in the work quality and reputation of contractors.

Keywords

Acknowledgements

The researchers acknowledge the assistance of the Palestinian Contractors Union, professional experts and An-Najah National University in Palestine.

Citation

Fatayer, F.A., Issa, A.Z., Abunemeh, M. and Dwikat, M.A.M. (2022), "Investigating the causes preventing the fulfillment of construction contract requirements", Engineering, Construction and Architectural Management, Vol. 29 No. 7, pp. 2577-2598. https://doi.org/10.1108/ECAM-01-2021-0083

Publisher

:

Emerald Publishing Limited

Copyright © 2021, Emerald Publishing Limited

Related articles