Abstract
This research introduces the development of a project-level cash flow forecasting model in construction stage based on the plamed earned value and the cost from a general contractors view on a jobsite. Most previous models have been developed to assist contractors in their pre-tendering or planning stage cash flow forecasts. The critical key to cash flow forecasting at the project level is how to build a cash-out model. The basic concept is to use moving weights of cost categories in a budget over project duration. The cost categories are classified to compile resources with almost the same time lags that are based on contracting payment condit ions and credit times given by suppliers or venders. For cash-in, net planned monthly-earned values are simply transferred to the ca sh-in forecast, to be applied there with billing time and retention money. Validation of the model involves applying data from on-goi ng4 projects in progress for 12 months. Based on the results of the comparative analyses through the simulation of the proposed mod el and the existing models, the proposed model is more accurate, flexible and simpler than traditional models to the employee of construction jobsite who is not oriented financial knowledge.
Similar content being viewed by others
References
Ahuja, H.N. and Walsh, M.A. (1983).Successful Methods in Cost Engineering, John Wiley & Son, New York, NY.
Ashley, D.B. and Teicholz, P.M. (1977). “Pre-Estimate Cash Flow Analysis.”Journal of Construction Division, ASCE, Vol. 103, No. CO3, pp. 369–379.
Bennett, J. and Ormerod, R.N. (1984). “Simulation Applied to Construction Projects.”Construction Management and Economics, Vol. 2, pp. 225–263.
Fondahl, J.W. and Bacarreza, R.R. (1972).Construction Contract Markup Related to Forecasted Cash Flow. Technical Report Construction Industry Institute Stanford University, CA.
Gates, M. and Scarpa, A. (1979). “Preliminary Cumulative Cash Flow Analysis.”Cost Engineering, Vol. 21, No. 6, pp. 243–249.
Hendrickson, C. and Au, T. (1989).Project Management For Construction: Fundamental Concepts for Owner, Engineer, Architects, and Builders, Prentice-Hill, Inc., Englewood, NJ.
Jepson, W.B. (1969). “Financial Control of Construction and Reducing the Element of Risk.”Contract Journal, April, pp. 862–864.
Kaka, A.P. and Price, A.D.F. (1991a). “Net Cash Flow Models: Are They Reliable?”Construction Management and Economics, Vol. 9, pp. 291–308.
Kaka, A.P. (1996). “Towards more Flexible and Accurate Cash Flow.”Construction Management and Economics, Vol. 14, pp. 35–44.
Kenley, R. and Wilson, O.D. (1989). “A Construction Project Net Cash Flow Model.”Construction Management and Economics, Vol. 7, pp. 3–18.
McCaffer, R. (1979). “Cash Flow Forecasting.”Quantity Surverying, August, pp. 22–26.
Meredith, J.R. and Mantel, S.J. Jr. (1995).Project Management A Management Approach—Third Edition, John Wiley & Son, Inc., New York, NY.
Navon, R. (1994b). “Company-Level Cash-Flow Management.”Journal of Construction Engineering and Management, ASCE, pp. 22–29.
Navon, R. (1995). “Resource-based Model for Automatic Cash-Flow Forecasting.”Construction Management and Economics, Vol. 13, pp. 501–510.
Navon, R. (1997). “Cash-Flow Forecasting and Management.”Construction Congress Proceeding, ASCE, New York, pp. 1056–1063.
Oberlender, G.D. (2000).Project Management for Engineering and Construction—Second Edition, McGraw-Hill, New York, NY.
Park, H.K. (2001).Cash Flow Forecasting Model Using Moving Weights of Cost Categories For General Contractors on Jobsite, Ph.D. dissertation, University of Wisconsin, Madison, Wisconsin, USA.
Peer, S. (1982). “Application of Cost-Flow Forecasting Models.”Journal of the Construction Division, Proceedings of ASCE, Vol. 108, No. CO2, pp. 226–232.
Peterman, G.G. (1973). “A Way to Forecast Cash Flow.”World Construction, October, pp. 17–22.
Reinschmidt, K.F. and Frank, W.E. (1976). “Construction Cash Flow Management System.”Journal of the Construction Division, Proceedings of ASCE, Vol. 102, No. CO4, pp. 615–627.
Russell, J.S. (1991). “Contractor Failure: Analysis.”Journal of Performance of Construction Facilities, ASCE, Vol. 5, No. 3, pp. 163–180.
Sears, G.A. (1981). “CPM/COST: An Integrated Approach.”Journal of the Construction Division, Proceedings of the ASCE, Vol. 107, No. CO2, pp. 227–238.
Singh, S. and Lakanathan, G. (1992). “Computer-Based Cash Flow Model.”Proceeding 36th Annual Trans., AM. Assoc. of Cost Engineers, AACE, R.5.1-R.5.14.
Trimble, R.G. (1982). Micro Computers in Construction Management.Building Technology and Management, Vol. 2, No. 2, pp. 11–13.
Author information
Authors and Affiliations
Corresponding author
Rights and permissions
About this article
Cite this article
Park, HK. Cash flow forecasting in construction project. KSCE J Civ Eng 8, 265–271 (2004). https://doi.org/10.1007/BF02836008
Received:
Accepted:
Issue Date:
DOI: https://doi.org/10.1007/BF02836008