A Metaheuristic Procedure Combined with 4D Simulation as an Alternative for the Scheduling Process of Housing Complexes

  • Conference paper
  • First Online:
Proceedings of the 18th International Conference on Computing in Civil and Building Engineering (ICCCBE 2020)

Part of the book series: Lecture Notes in Civil Engineering ((LNCE,volume 98))

  • 5775 Accesses

Abstract

The present work focuses on the application of a metaheuristic procedure, represented by a Genetic Algorithm, in the search of better alternatives for the organization of activities in the construction of housing complexes. Therefore, the algorithm is implemented in order to solve the Resource-Constrained Project Scheduling Problem – RCPSP. The problem modeling is adapted to the type of project in question, where, at first, the activity network of a single housing unit is defined through an activity-on-the-node graph and afterwards the Line of Balance method is used in order to determine the start and finish dates of all the other repetitive activities of the project. In order to test the efficiency of the algorithm, numerous experiments are performed with project instances from the PSPLIB, a specific benchmark database for the RCPSP, available online. Finally, in order to better visualize the schedules obtained in the optimization phase, a 4D simulation of a schedule for the execution of a housing complex, generated with the metaheuristic procedure, is performed with the software Autodesk Navisworks. The simulation phase allows the visualization of the projects constructability, makes it possible to confirm if the algorithm-generated schedule follows a logical sequence, as well as it supports the decision-making about the best execution alternatives.

This is a preview of subscription content, log in via an institution to check access.

Access this chapter

Chapter
USD 29.95
Price excludes VAT (USA)
  • Available as PDF
  • Read on any device
  • Instant download
  • Own it forever
eBook
USD 259.00
Price excludes VAT (USA)
  • Available as EPUB and PDF
  • Read on any device
  • Instant download
  • Own it forever
Softcover Book
USD 329.99
Price excludes VAT (USA)
  • Compact, lightweight edition
  • Dispatched in 3 to 5 business days
  • Free shipping worldwide - see info
Hardcover Book
USD 329.99
Price excludes VAT (USA)
  • Durable hardcover edition
  • Dispatched in 3 to 5 business days
  • Free shipping worldwide - see info

Tax calculation will be finalised at checkout

Purchases are for personal use only

Institutional subscriptions

References

  • Amiri, R., Sardroud, J.M., de Soto, B.G.: BIM-based applications of metaheuristic algorithms to support the decision-making process: uses in the planning of construction site layout. Procedia Eng. 196, 558–564 (2017)

    Article  Google Scholar 

  • Bäck, T., Fogel, D.B., Michalewicz, Z. (eds.): Evolutionary Computation 1: Basic Algorithms and Operators. CRC Press, Boca Raton (2018)

    Google Scholar 

  • Bettemir, Ö.H., Sonmez, R.: Hybrid genetic algorithm with simulated annealing for resource-constrained project scheduling. J. Manag. Eng. 31, 04014082 (2015)

    Article  Google Scholar 

  • Bezerra, P.H.P., Scheer, S.: Uso de Building Information Modeling para o aprimoramento e automatização do planejamento de obras: revisão sistemática da literatura. In: Encontro Nacional De Tecnologia Do Ambiente Construído. ANTAC, Porto Alegre (2018)

    Google Scholar 

  • Bezerra, P.H.P., de Paula Lacerda Santos, A., Scheer, S.: BIM no planejamento de empreendimentos com sistemas de painéis pré-fabricados: uma alternativa para obras de habitação social. PARC Pesquisa em Arquitetura e Construção (2018)

    Google Scholar 

  • Biotto, C.N., Formoso, C.T., Isatto, E.L.: Método para o uso da Modelagem BIM 4D na Gestão da Produção em Empreendimentos de Construção. In: Simpósio Brasileiro de Qualidade do Projeto No Ambiente Construído; Encontro de Tecnologia de Informação E Comunicação Na Construção, Campinas. ANTAC, Porto Alegre (2013)

    Google Scholar 

  • de Brito, D.M., de Andrade Marques Ferreira, E.: Avaliação de estratégias para representação e análise do planejamento e controle de obras utilizando modelos BIM 4D. Ambiente Construído, Porto Alegre 15, 203–223 (2015)

    Article  Google Scholar 

  • Cheng, M.-Y., Prayogo, D., Tran, D.-H.: Optimizing multiple-resources leveling in multiple projects using discrete symbiotic organisms search. J. Comput. Civil Eng. 30, 04015036 (2016)

    Article  Google Scholar 

  • Faghihi, V., Reinschmidt, K.F., Kang, J.H.: Construction scheduling using genetic algorithm based on building information model. Expert Syst. Appl. 41, 7565–7578 (2014)

    Article  Google Scholar 

  • Faghihi, V., et al.: Automation in construction scheduling: A review of the literature. Int. J. Adv. Manufact. Technol. 81, 1845–1856 (2015)

    Article  Google Scholar 

  • Ghoddousi, P., et al.: Multi-mode resource-constrained discrete time–cost-resource optimization in project scheduling using non-dominated sorting genetic algorithm. Autom. Constr. 30, 216–227 (2013)

    Article  Google Scholar 

  • Giran, O., Temur, R., Bekdaş, G.: Resource constrained project scheduling by harmony search algorithm. KSCE J. Civil Eng. 21, 479–487 (2017)

    Article  Google Scholar 

  • Gledson, B.J., Greenwood, D.J.: Surveying the extent and use of 4D BIM in the UK. J. Inf. Technol. Constr. (ITcon) 21, 57–71 (2016)

    Google Scholar 

  • Goldbarg, M.C., Goldbarg, E.G., Luna, H.P.L.: Otimização combinatória e metaheurísticas, 1st edn. Elsevier, Rio de Janeiro (2016)

    Google Scholar 

  • Hillier, F.S., Lieberman, G.J.: Introdução à pesquisa operacional. AMGH, Porto Alegre (2010)

    Google Scholar 

  • Hyari, K., El-Rayes, K.: Optimal planning and scheduling for repetitive construction projects. J. Manage. Eng. 22, 11–19 (2006)

    Article  Google Scholar 

  • Ichihara, J.A.: Um método de solução heurístico para a programação de edifícios dotados de múltiplos pavimentos-tipo. Universidade Federal de Santa Catarina, Florianópolis (1999)

    Google Scholar 

  • Kim, J.-L., Ellis Jr., R.D.: Permutation-based elitist genetic algorithm for optimization of large-sized resource-constrained project scheduling. J. Constr. Eng. Manage. 134, 904–913 (2008)

    Article  Google Scholar 

  • Klimek, M.: A genetic algorithm for the project scheduling with the resource constraints. Annales Universitatis Mariae Curie-Sklodowska, Sectio AI-Informatica 10, 117–130 (2010)

    Article  Google Scholar 

  • Kolisch, R., Hartmann, S.: Heuristic algorithms for the resource-constrained project scheduling problem: Classification and computational analysis. In: Węglarz, J. (ed.) Project Scheduling. International Series in Operations Research & Management Science, vol. 14, pp. 147–178. Springer, Boston (1999)

    Chapter  Google Scholar 

  • Kolisch, R., Sprecher, A.: PSPLIB – a project scheduling problem library. Eur. J. Oper. Res. 96, 205–216 (1996)

    Article  Google Scholar 

  • Limmer, C.V.: Planejamento, orçamentação e controle de projetos e obras. LTC, Rio de Janeiro (1997)

    Google Scholar 

  • Liu, H., Al-Hussein, M., Lu, M.: BIM-based integrated approach for detailed construction scheduling under resource constraints. Autom. Constr. 53, 29–43 (2015)

    Article  Google Scholar 

  • Marzouk, M., et al.: A simulation optimisation tool for planning of low-income housing projects. Civ. Eng. Environ. Syst. 31, 51–63 (2014)

    Article  Google Scholar 

  • Marzouk, M., et al.: An optimization algorithm for simulation-based planning of low-income housing projects. J. Adv. Res. 1, 291–300 (2010)

    Article  Google Scholar 

  • Mathew, J., et al.: Multi objective optimization for scheduling repetitive projects using GA. Procedia Technol. 25, 1072–1079 (2016)

    Article  Google Scholar 

  • Mendes Jr., R.: Programação da produção na construção de edifícios de múltiplos pavimentos. Universidade Federal de Santa Catarina, Florianópolis (1999)

    Google Scholar 

  • Potgieter, I.J., van Rooyen, G.C.: Maximizing slack in resource-constrained schedules: a heuristic approach. J. Comput. Civ. Eng. 30, 04016018 (2016)

    Article  Google Scholar 

Download references

Author information

Authors and Affiliations

Authors

Corresponding author

Correspondence to Sergio Scheer .

Editor information

Editors and Affiliations

Rights and permissions

Reprints and permissions

Copyright information

© 2021 The Editor(s) (if applicable) and The Author(s), under exclusive license to Springer Nature Switzerland AG

About this paper

Check for updates. Verify currency and authenticity via CrossMark

Cite this paper

Bezerra, P., Scheer, S. (2021). A Metaheuristic Procedure Combined with 4D Simulation as an Alternative for the Scheduling Process of Housing Complexes. In: Toledo Santos, E., Scheer, S. (eds) Proceedings of the 18th International Conference on Computing in Civil and Building Engineering. ICCCBE 2020. Lecture Notes in Civil Engineering, vol 98. Springer, Cham. https://doi.org/10.1007/978-3-030-51295-8_41

Download citation

  • DOI: https://doi.org/10.1007/978-3-030-51295-8_41

  • Published:

  • Publisher Name: Springer, Cham

  • Print ISBN: 978-3-030-51294-1

  • Online ISBN: 978-3-030-51295-8

  • eBook Packages: EngineeringEngineering (R0)

Publish with us

Policies and ethics