南方电网35 kV±200 Mvar链式STATCOM现场试运行
作者:
作者单位:

1.广东电网公司东莞供电局,广东省东莞市523120;2.辽宁科技大学,辽宁省鞍山市114051; 3.荣信电力电子股份有限公司,辽宁省鞍山市114051

摘要:

介绍了南方电网35kV±200 Mvar链式静止同步补偿器(STATCOM)的现场测试与试运 行,重点对启停试验、运行试验、动态特性试验、双套协调控制试验、运行范围和热运行试验、冗余试 验中的一些技术问题进行了讨论。现场试验表明:STATCOM启停、紧急停机、定无功和定电压控制、双套协调控制等符合设计要求,运行稳定;阶越增减20Mvar时,STATCOM能在35 ms内完成输出调节;投切电容器或电抗器时,STATCOM能在20ms内完成调节,过渡平稳,无冲击;阀组 单元故障模拟试验的闭锁、旁路、重启和跳闸保护符合设计要求。试验结果也表明兼顾500 kV和220 kV母线电压的双目标优化控制策略的STATCOM直流侧电压平衡问题、输出电流谐波以及节能运行仍需深入研究。

关键词:

基金项目:

“十一五”国家科技支撑计划项目(2007BAA10B02)

通信作者:

作者简介:


On-site Commissioning of35kV±200Mvar Cascade STATCOM in China Southern Power Grid
Author:
Affiliation:

1.Dongguan Power Supply Bureau,Guangdong Power Grid Corporation,Dongguan523120,China; 2.University of Science and Technology Liaoning,Anshan114051,China; 3.Rongxin Power Electronic Co.Ltd.,Anshan114051,China

Abstract:

The on-site test and the commissioning of35kV±200Mvar cascade static synchronous compensator(STATCOM) in China Southern power grid are introduced.The technical matters such as:start-up and stop test,operation test,dynamic characteristic test,two-set coordinated controlling test,operating range and hot operation test,and redundance test are discussed.The on-site test results show that:STATCOM start-up and stop,the emergency stop,the control with constant var output and constant voltage,and coordinated controlling of two sets,etc.meet the design requirements,and the operation is stable;STATCOM can complete the output regulation within35ms under±20Mvar step change;when capacitor or reactor is switched on or off,STATCOM can complete the output regulation within20ms with a smooth transition without shock.The valve unit fault simulating test shows that the lock,the bypass,the restart and the tripping protection meet the design requirements.The test results also show that the DC voltage balance problem of STATCOM with considering the double objective optimization control strategy of500kV and 220 kV bus voltage,the output current harmonics and the energy-saving operation are still need to be studied further.

Keywords:

Foundation:
引用本文
[1]黄伟雄,胡广振,王永源,等.南方电网35 kV±200 Mvar链式STATCOM现场试运行[J].电力系统自动化,2013,37(19):122-131. DOI:10.7500/AEPS201212173.
HUANG Weixiong, HU Guangzhen, WANG Yongyuan, et al. On-site Commissioning of35kV±200Mvar Cascade STATCOM in China Southern Power Grid[J]. Automation of Electric Power Systems, 2013, 37(19):122-131. DOI:10.7500/AEPS201212173.