Research articleFrom declared asset retirement obligations to a decommissioning cost estimate for onshore crude oil fields in Nigeria
Graphical abstract
Introduction
Petroleum mineral resources are finite and non-renewable, and as such cannot be extracted in perpetuity. In most crude oil producing countries, several oil fields are beginning to experience significant production declines. The International Energy Agency (IEA, 2013) observed that the average production-weighted decline rate worldwide was approximately 6.0% in 2012 for post-peak fields. S&P Global Platts (2016) projected that the production decline rate for non-OPEC producers was approximately 5% in 2016 and that an even higher rate held for OPEC producers. These observations support the position of Simmons (2002) that eventually, most of the world's current population of giant fields will all be in decline and their economic operations will cease.
The petroleum business cycle runs from field exploration, development, production to decommissioning and abandonment, when a field becomes unprofitable for production. With deterioration in integrity of infrastructures due to old age, associated production decline, and increasing environmental concerns, decommissioning of oil fields has become a very important activity and a contentious topic in recent times. Wood Mackenzie (2016) estimated the cost of decommissioning for facilities in the North Sea to be approximately US$ 40 billions. According to the UK's fiscal policy, the government is expected to pay approximately US$ 19 billions of this cost as tax credits given to the oil companies after completion of decommissioning activities. In the Gulf of Mexico (GoM), triggered by new US regulations, DecomWorld (2015) estimated decommissioning costs to be approximately US$26 billion. Rogers and Atkins (2015) observed that approximately 50% of the total debt in the oil and gas industry is management's estimated cost of settling decommissioning liabilities. In Nigeria, the multinational oil companies (MOCs) are beginning to divest from Nigerian onshore fields and to sell their equity to local or small independent companies. The Nigerian Vanguard newspaper (2013) reported a rising trend in divestment of onshore fields by MOCs that started in 2009, coming up to an approximately 50% total stake as at 2013. Obviously, to the MOCs, the fields have become less attractive in the face of one or a combination of production, financial, and sociopolitical factors. The local and small independent companies acquiring these fields are not as financially as robust as the MOCs. With the decline in production, there will be less revenue coming from the onshore fields. If the cost of decommissioning is huge, it is probable that the small independent companies may abandon the fields without proper decommissioning; and improperly decommissioned facilities will lead to environmental degradation.
Decommissioning and abandonment requirements are not prescriptively stated in Nigeria laws and guidelines, beyond an aspiration to remove facilities at the end of their economic life and according to international best practices (Ibebuike, 2013, West, 2014, Salawu, 2014). Good environmental stewardship will call for all crude oil production facilities to be removed and the environment restored to its preproduction conditions (Ekhator, 2016) or to a better socioeconomic and environmental condition, for current and future stakeholders. This will be the expected sustainable decommissioning and responsible mineral development approach.
While it appears that the dynamics of sustainable development, decommissioning, and end of field life (EOFL) for mineral resources are common observations globally, the sense of the cost of decommissioning liabilities and related discussions is minimal in Nigeria. There may be several contributory factors to this situation, but there should be no acceptable reason for failure to have a publicly accessible cost estimate and plan for decommissioning and associated environmental liabilities in Nigeria, especially the aged onshore crude oil fields.
Ruivo and Morooka (2001) defined decommissioning as “the dismantling, decontamination, and removal of process equipment and facility structures” at the end of a field's economic life. It is a multidiscipline exercise, involving engineering, financial, sociopolitical, environmental, health, and safety disciplines. The terms “abandonment” and “decommissioning” are often used interchangeably, although according to Ayoade (2002), industry operators prefer to use decommissioning, which does not connote voluntary relinquishment in the way abandonment does. In financial reports, some operators describe their decommissioning liabilities as Asset Retirement Obligation (ARO), Decommissioning, Dismantlement, and Restoration (DD&R) or Dismantlement, Removal, and Restoration (DR&R). Smith et al. (2000) and Lawal (2008) noted that there was no recognition of any petroleum-related activities continuing beyond the production phase in Nigeria's Joint Venture (JV) agreements. As further argued by Lawal, this implied that decommissioning was not thought about when the agreements were drafted and signed. Now that the EOFL for these fields is foreseeable, with attendant implications for the revenue and sociopolitical aspects of the nation, quantifying cost implications of decommissioning liabilities, i.e. their dismantlement, removal, and restoration of the environment, has become important.
Accountants and investors like to know the cost of decommissioning liabilities to help them evaluate the sustainability of investment in oil companies. Fields with complicated decommissioning obligations that can cost as much as the anticipated remaining profit from them, will not be attractive to investors. As smaller independent companies that are less financially and technically robust take over operatorship of these fields, the risk of an operator defaulting on its decommissioning liabilities will increase. Compared to the MOCs, they may not have much corporate environmental reputation to uphold, and therefore could easily default. If an operator fails to complete the decommissioning of its facilities, the government, which by extension is the public, will have to pay for the completion of decommissioning of the facilities like the orphan wells programs in the US (Hesson, 2006), or else the environment will be left polluted. In mature fields like the UK Continental Shelf (UKCS), government policy requires operators to remove all assets, unless otherwise approved. Currently under the US Superfund program and also in the UK, all operators that have been associated with an asset at any time in its economic life are held jointly and severally liable for the decommissioning liabilities (West, 2014, Wetmore, 2014). On the contrary, there is no similar explicit policy objective in Nigeria. The new Petroleum Industry Bill is intended to incorporate a similar objective (Dawodu, 2016). However, enforcing it on foreign-parented companies like the MOCs will be difficult, especially after they have divested their assets to local companies and left Nigeria. According to Schaps and George (2017), a court in the UK has held that Shell—an MOC in Nigeria—cannot be taken to a UK court in a dispute over environmental liabilities from its operations in Nigeria. A revised regulatory approach may be required for the decommissioning of crude oil fields in Nigeria. To develop and administer an efficient policy for decommissioning, the cost of meeting decommissioning and its associated environmental liabilities needs to be known by the government and public. From a literature search and to the best of our knowledge, there is no rough order of magnitude (ROM) estimate or any published attempt at generating cost estimates for decommissioning and associated environmental liabilities of onshore crude oil fields in Nigeria. This study seeks to address this knowledge gap. A rough order of magnitude (ROM) cost estimate is a cost estimate prepared at the early stage of a project life cycle when scope definition is very minimal and has a low accuracy range of +50% and −50%. It is not a detail cost estimate and recommended for making high level decisions at the early stage of a project. (PMBOK, 2013). Absence of publicly accessible cost estimates for decommissioning liabilities in Nigeria can be attributed to several factors like low level of public awareness about decommissioning, confidentially of information related to decommissioning, little emphasis on decommissioning phase in the regulatory frameworks etc., (Lawal, 2008, Ibebuike, 2013, Stakeholder Democracy Network SDN, 2015). The research question is therefore: can we get reliable public accessible data to estimate and establish a high-level aggregate cost of decommissioning and associated environmental liabilities from onshore fields in Nigeria? This will help to facilitate discussions and policy development for the decommissioning of onshore fields in Nigeria, events that—contrary to assumptions held by the public—may commence sooner than later.
Section snippets
Nigeria and its crude oil production profile
Crude oil fields in Nigeria are generally classified into either offshore fields or onshore fields, as illustrated in Fig. 1. According to NAPIMS (2016), offshore fields are located in the continental shelf of the Atlantic Ocean at water depths of 100 m or deeper. Onshore fields are located on land and shallow waters of less than approximately 100 m deep, which are mainly mangrove swamp locations. Empirical observation of the historical crude oil production profile for Nigeria in Fig. 2 shows
Nigeria onshore fields and facilities
Nigeria onshore fields are spatially dispersed and widespread with vast pipeline and flowline networks. Most of the onshore field infrastructure was manufactured, fabricated, and installed in the late 1950s and 1960s. The facilities are getting old and in some cases, obsolescence has set in. Without some viable and exciting economic prospects on the horizon for these fields, an upgrade or change-out of this infrastructure may not be supported.
Most of the onshore facilities in Nigeria share
Sustainable decommissioning and cost estimating needs for decommissioning liabilities of onshore fields in Nigeria
A sustainable approach to decommissioning will attempt to assess the risk associated with the decommissioning of Nigeria's onshore fields, identify credible scenarios and associated time lines, and seek an optimal socioeconomic mitigation strategy. Nigeria is still at a very early stage when it comes to description and development of a plan towards decommissioning of its onshore fields.
The investigations of this study reveal widespread vagueness on what decommissioning entails and either denial
Asset retirement obligations or decommissioning liabilities in annual financial reports
The legal and compulsory responsibilities associated with decommissioning liabilities are better presented when described from an asset retirement obligation perspective. According to Kaiser (2015), “AROs are those [assets] for which there is legal obligation to settle under existing or enacted law, statute, written or oral contract,” even though their actual execution may be in the future. This brings into play the time value of money. Cost of ARO declared in financial reports is the present
Estimating generic costs of decommissioning liabilities for Nigeria onshore fields using ARO data from annual corporate financial reports
The method in Fig. 5 introduced in this study to calculate cost estimates for decommissioning liabilities, is basically a reverse of the process used to determine the declared cost of ARO in Fig. 4. As further illustrated in Appendix I, the first step is to find annual financial reports for companies that operate only in Nigeria onshore fields. This approach could also be applied to any entity in the world that operates only in a particular region. Public domains searched include company
Limitations
The data set used in this study to estimate the aggregate cost of decommissioning for onshore fields in Nigeria is small, even though deemed representative enough for an initial generic and aggregate rough order of magnitude cost of decommissioning. Scope has been aggregated for all facilities with the assumption that averaging over a larger number of facilities will address the challenges posed by differences in size and scope of individual facilities. The results cannot therefore, be used for
References (53)
Public participation and environmental impact assessment: purposes, implications, and lessons for public policy making
Environ. Impact Assess. Rev.
(2010)- et al.
Simulation Modeling and Analysis with Arena
(2010) AACE International Recommended Practice No.18R-97 Recommended Practice 18R-97: Cost Estimate Classification System– as Applied in Engineering, Procurement and Construction for the Process Industries
(2016)Disused Offshore Installations and Pipelines: towards Sustainable Decommissioning
(2002)Effects of IFRS adoption on the financial reports of Nigerian listed entities: the case of oil and gas companies
The Macrotheme Review
(2013)BP Statistical Review of World Energy June 2016. London
(2016)Campbell's Atlas of Oil and Gas Depletion
(2013)Divesture of Upstream Oil and Gas Assets by IOCs in Nigeria: Examination of Selected Legal Issues
(2016)Offshore Decommissioning Report 2015
(2015)IOCs Divestments in Nigeria Opportunities: Challenges, and Outlook. Middle Africa Insight Series| Energy, Oil and Gas. Ecobank Research
(2013)
Public regulation of the oil and gas industry in Nigeria: an evaluation
Ann. Survey Int. Comp. Law
Eland oil& Gas PLC Annual Report and Financial Statements 2015
Financial Reporting Developments: a Comprehensive Guide. Asset Retirement Obligations
State Presses BLM on Legacy Well Issue
The Eureka Canyon oil field: a case history
HMT Green Book: Supplementary Guidance
Oil and Gas Assets Trading and Decommissioning Liability Issues in Nigeria
World Energy Outlook 2013
Upstream Capital Cost Index
A new approach to decommissioning cost estimation using settled liability data
Eng. Econ.
Decommissioning cost estimation for deepwater floating structures in the US Gulf of Mexico
Ships and Offshore Struct.
A Review and Update of Supplemental Bonding Requirements in the Gulf of Mexico
Environmental risk and well integrity of plugged and abandoned wells
A private contractor's approach to decommissioning costs
Energy J.
Decommissioning Accountability ‘expectations Gap’: the Perceptions of Stakeholders in Nigerian Oil and Gas Industry
Representations of reversal: an exploration of Simpson's Paradox
Cited by (4)
Crude oil market and Nigerian stocks: An asymmetric information spillover approach
2022, International Journal of Finance and EconomicsGeothermal energy extraction using abandoned oil and gas wells: Techno-economic and policy review
2022, International Journal of Energy ResearchImprovement of the upstream project valuation in consideration of abandonment expenditure ABEX uncertainties
2020, Society of Petroleum Engineers - SPE Symposium: Decommissioning and Abandonment 2019Improvement of the upstream project valuation in consideration of abandonment expenditure ABEX uncertainties
2020, International Petroleum Technology Conference 2020, IPTC 2020